Chapter 6 - Schedule Management Flashcards
Plan Schedule Management process
- Involves documenting how you will plan, manage, and control the project to the schedule baseline, and how you will manage schedule variances
Answers questions like:
- What approach will we take to plan the schedule for the project? Who will be involved?
- What processes and procedures will we use to create the schedule?
Key output of the Plan Schedule Management process?
Schedule management plan
Schedule management plan
- Part of the PMP
- Helps make the estimating and schedule development process faster by speciyfing how you will plan, manage, and control the project
Define Activities process
Taking the work packages created in the WBS and decomposing them into the activities that are required to produce the work package deliverables
When decomposing work packages, how do you know when you’ve decomposed enough?
Activities should be at a level small enough to estimate, schedule, monitor, and control
What happens after you define acitivites, i.e., decompose work packages?
Sequence activities
What do you need to define activities?
- Schedule management plan - gives info about approved methodology for scheduling
- Scope baseline - provides info about what is included in project scope
- OPAs
When is decomposition used for Define Activities process in schedule management, and for Create WBS process in scope management?
Define Activities
When work packages are decomposed into activities to produce them
Create WBS
When deliverables are decomposed into smaller deliverables
Rolling wave planning
- Plan to a higher level, and then develop more detailed plans when the work is to be done
- In other words, plan activities to the detail needed to manage the work just before you are ready to start the project
- Form of progressive elaboration
What does the Define Activities process result in?
An activity list, which includes all activities required to complete the project, and details regarding project activities
Sequence Activities process
Taking the activities and sequencing them in the order in which the work will be performed
What does sequencing activities result in?
A network diagram
What does a network diagram represent/show?
- In it’s pure form, it shows just dependencies, i.e., logical relationships
- If activity duration estimates and leads and lags are included, it also shows the critical path
- If plotted out against time, it shows a time scaled schedule network diagram
How are most network diagrams created today?
- Using the Precedence Diagramming Method (PDM)
- Old method = Graphical Evaluation and Review Technique (GERT)
Precedence Diagramming Method (PDM)
- Nodes, a.k.a. boxes, represent activities
- Arrowsshowactivity dependencies
Different types of logical relationships between activities
- Finish to start (FS)
- Start to start (SS)
- Finish to finish (FF)
- Start to Finish (SF)
Finish to start (FS)
- An activity must finish before the successor can start
- MOST COMMON!
- Example: you must finish digging a hole before you can start planting the tree
Start to start (SS)
- An activity must start before the successor can start
- Example: you must start desgining in order to have enough of the design completed to start coding
Finish to finish (FF)
- An activity must finish before the successor can finish
- Example: you must finish testing before you can finish documentation
Start to finish (SF)
- An activity must start before the successor can finish
- RARELY USED
Types of dependencies
- Mandatory dependency (hard logic)
- Discretionary dependency (preferred, preferrential, or soft logic)
- External dependency
- Internal dependency
Mandatory dependency (hard logic)
Inherent in the nature of work, or required by a contract
Discretionary dependency (preferred, preferrential, or soft logic)
- The way an organization has chosen to have work performed
- You can change this type of dependency if necessary
- Important when analyzing how to compress the schedule to decrease project duration, i.e., fast track the project
External dependency
Based on the needs or desires of a party outside the project (for example, government, suppliers, etc.)
Internal dependency
Based on the needs of the project and may be something the team can control
Who identifies what type of dependencies?
- Project team = mandatory and discretionary
- PM = external and internal
Lead
Used to indicate that an activity can start before its predeccesor activity is completed
Lag
Waiting time inserted between activities
Path convergence
When an activity has two or more activities directly preceding it, i.e., two activities run into the same activity once complete
Path divergence
When an activity has two or more successor activities directly following it
What do path convergence and divergence indicate?
Greater risk within impacted activities