Chapter 63, Project Management Flashcards

1
Q

Project management can be divided into 4 processes

A
  • planning
  • executing
  • monitoring
  • completing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical Path Analysis

A

the process that allows for the overall time of a project to be calculated and to allow a diagrammatic network to be drawn which shows when activities should start and finish
See Chapter 63 to learn how to do this

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Dummy Activity

A

an activity with no significant time but is an essential link between other activities. Marked with a dotted line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Floats

A

shows how much time an activity may overrun before it as an effect on either the next activity or the project as a whole

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Total Float

A

the longest time which any activities start may be delayed without affecting the length of the project as whole

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Free Float

A

the effect upon the next activity and not the project as a whole; these delays are not as serious

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Gantt Charts

A

a graphical representation of the order and duration of given tasks within a project
see page 448

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Benefits of Critical PAth analysis

A
  • simplistic form of communication
  • a simple way to calculate
  • helps a business see when cahs will be needed
  • allows to see consequences of potential delays
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Limitations of Critical Path Analysis

A
  • depends on accuracy of activity times

- only considers time not cost implications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Benefits of Gantt Chart

A
  • it’s simplistic

- shows both time and resource allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Limitations of Gantt Chart

A
  • does not show critical activities

- calculation of floats is difficult

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PERT

A

statistical tool used to predict time taken to complete tasks but more pessimistically

Optimistic time + 4 x likely time + Pessimistic time / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Advantages of PERT

A
  • more realistic
  • a simple formula to apply
  • help decision making
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Disadvantages of PERT

A
  • gauging the optimistic times is guesswork

- complicated to use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly