Chapter 6: Project Management Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

project management techniques which have been created out of the need of industrial and military establishments to plan, schedule and control complex projects

A

PERT-CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

primarily to simplify the planning and scheduling the large and complex projects to handle uncertain activity times, initially for the Polaris missile nuclear submarine project

A

PERT/ Program Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

statistical tool used in project management which was designed to analyze and represent the tasks involve in completing a given projects, especially the time needed to complete the task and minimum time needed to complete the total project

A

PERT/ Program Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

It is for industrial projects for which activity times generally were known, the computation was design for a computer and was first applied to the construction of a new chemical plant

A

CPM/ Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

developed by U.S. Navy in 1957

A

PERT/ Program Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

developed by DuPont & Remington Rand in 1957

A

CPM/ Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

have been used to plan, schedule, and control a wide variety of project

A

PERT-CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Managerial Functions

A

-Planning
-Scheduling
-Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Function of PERT-CPM

A

a. Research and design of new products and processes
b. Construction of buildings and highways
c. Maintenance of large and complex equipment
d. Design and installation of new systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PERT-CPM can answer the ff:

A

a. Total time to complete project
b. Scheduled start and finish dates for each specific activity
c. Critical Activities
d. Exact time/days/weeks that non-critical activities can be delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

events that immediately precedes the next event without any intervention

A

predecessor event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

an event that immediately follows a previous event without any intervention

A

successor event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Earliest Start/ ES

A

maximum Earliest Finish/ 0 for no predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Earliest Finish

A

Earliest Start + Completion Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Latest Finish

A

minimum Latest Start/ maximum Earliest Finish for not immediate predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Latest Start

A

Latest Finish - Completion Time

17
Q

path of the activities, from the Start node to the Finish node, with 0 slack times

A

Critical Path

18
Q

Project Completion Time

A

equal the maximum Earliest Finish