Chapter 6 - PM Flashcards
A table that lists activities and the dates on which you plan to start and end them
Activities report
Work required to move from one event to the next in a project
Activity
A type of network diaram; also referred to as activity-in-the-node or precedence diagramming
Activity-in-the-box
When on calendar a resource will be available
Availability
Schedule process of starting the end of a proj & working back twd the beginning, identifying activities as you go & estimating durations that eventually will add up to the amount of time the project has been given
Backing in
Finish-to-start analysis by a proj mgr to determine critical paths and earliest start and finish dates
Backward pass
Productivity per unit time period
Capacity
A sequence of activities in a project that takes the longest time to complete
Critical path
A network diagram that uses deterministic, certain estimates but includes both time and cost estimates to allow time/cost-in-the-box format
Critical path method (CPM) charts
Another term for a network diagram in either activity-on-the-arrow or activity-in-the-box format
Dependency diagram
Relationships the proj mgr or project team chooses to est. btwn activities
Discretionary relationships
Activity with 0 span time that’s used to represent a required dependency btwn event
Dummy activity
How long each indiv activity will take in a project
Duration
The earliest date that someone can possibly finish an activity
Earliest finish date
The earliest date that someone can possibly start an activity
Earliest start date
A significant occurrence in the life of the project also called a milestone or a delvierable. Events take no time and consume no resources, they occur instantaneously
Event
Schedule process in which you perform two or more activities at the same time to reduce the overall time to complete a project
Fast tracking
Start-to-finish analysis by a proj mgr at the beg of the proj to see how fast the activities can be completed
Forward pass
An amount of time project managers add to an estimate of span time just to be safe
Fudge factor
A graph illustrating on a time line when each activity will start, be performed, and end
Gantt chart
A network diagram technique that combines structures such as flowgrapsh, probabilistic networks, and decision tress, creating a complex schedule
Graphical evaluation and review technique (GERT)
Term given to an activity that upon completion, can allow someone to start on the following activity
Immediate predecessor
A table that lists events and the dates on which you plan to reach them
Key-events report