Chapter 6 Flashcards

1
Q

Cost management

A
  • management of costs, reflects the project’s strategic goals, mission statement and business plan
  • encompasses data collection, cost accounting and cost control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost accounting and cost control

A

main mechanisms for identifying and maintaining control over project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost estimation

A
  • process that creates reasonable budget baseline for the project
  • is the first step you take when determining is a project is viable
  • identifies project resources, creating a time-phased budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Common sources of project cost: Labor

A

costs related to personnel to be employed in the development of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Common sources of project cost: materials

A

material costs to apply to the specific equipment, required to complete tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Common sources of project cost: subcontractors

A

cost of services to be provided to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Common sources of project cost: equipment and facilities

A

costs of hiring equipment or facilities to be used in the development of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

common sources of project cost: travel

A

expenses related to business travel (car rental, airfare, hotels, meals, etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Types of costs

A
  • Direct and indirect
  • Fixed and variable
  • Recurring and nonrecurring
  • Normal and Expedited
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Direct costs and indirect costs

A
  • direct costs are costs used to execute project activities (labour and materials)
  • indirect costs are not used for the execution of the project (overhead and general administration)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Fixed and Variable costs

A
  • fixed costs do not vary
  • variable costs increase in direct proportion to usage level
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Recurring and nonrecurring

A
  • recurring typically continue to operate over the project’s life cycle (material, labour, logistics, sales costs)
  • nonrecurring costs are applied once at the beginning or end of the project (personnel training, marketing analysis…)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Normal and Expedited costs

A
  • normal costs are carried out when the project is carried out as planned (labour, materials)
  • expedited costs are unplanned and extra costs (paying overtime or temporary workers)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What cost is direct labour?

A

direct cost, also recurring, fixed, and normal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What cost would a building lease be considered?

A

indirect (or overhead), recurring, fixed, normal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost estimation principles

A
  1. the clearer you define the project’s costs in the beginning, the lesser the chance of making mistakes
  2. if your initial cost is accurate, it is very likely that your project budget will match your project cost (higher chance of not going over the budget)
17
Q

Disaggregated basis

A

breaking down project costs into smaller parts called “work packages” when estimating costs, you figure the cost of each work package and then you add them all up for the final estimated cost

18
Q

Rough estimates

A

early estimates made when you don’t have enough time or information, gives a basic idea (30% accuracy)

19
Q

Comparative estimates

A

historical data from past projects to estimate the cost of the current one (15% accuracy)

20
Q

Feasibility estimates

A

based on real numbers after the project design is done, often done in construction where material costs can be calculated based on quantities (10%)

21
Q

Definitive estimates

A

can only be made after most of the design is complete (5% accuracy)

22
Q

Problems with cost estimation: low initial estimates

A

happens when the project costs are misunderstood either on purpose (to make it look cheaper so that it gets approved), or by mistake, and always leads to spending more than planned

23
Q

Problems with cost estimation: unexpected technical difficulties

A

estimating costs can go wrong when people estimate that there wont be technical problems, good estimates need to consider technical issues, delays, and other risks

24
Q

Problems with cost estimation: lack of definition

A

poorly defined features and objectives lead to poor cost estimates

25
Q

Problems with cost estimation: specification changes

A

changes to the project’s goals or features during development often increase costs

26
Q

Problems with cost estimation: external factors

A

things like inflation, raw material shortage, or other economic impacts can increase costs

27
Q

Creating a project budget

A
  • involves planning resources, goals, and timeline needed to complete the project
  • the budget must match the project activities outlined in the WBS which helps create the project schedule, the budget then assigns the necessary resources to meet that schedule
28
Q

How can cost data be collected and interpreted?

A

through a top-down or bottom-up budgeting procedure

29
Q

Activity based costing (ABC)

A

method that assigns costs first to activities, and then to the projects based on each project’s use of resources

30
Q

Top-down budgeting

A
  • starts with senior manager’s estimates of costs for future projects (first total cost, and then major work packages costs)
  • estimates are passed down the hierarchy to the net functional levels, where additional information is collected
  • each step down the hierarchy, the project becomes more detailed until the people doing the actual work provide input on the specific cost for each task
31
Q

Bottom-up budgeting

A
  • starts by looking at individual tasks in WBS
  • the costs for all activities are then added together: first for individual tasks, then for work packages, then for deliverables and finally for the overall project
32
Q

Activity-based costing (ABC) steps

A
  1. assign costs to activities
  2. identify cost drivers (factors that cause costs for each activity)
  3. calculate cost rate per unit of the cost driver (cost rate/unit = $cost/hour)
  4. multiply the cost driver rate by the number of units used (Labour cost= ($40/hr) x (80 hours)= $3200)
33
Q

Time-phased budget

A

allocates costs across both project activities and the anticipated time in which the budget is to be expended

34
Q

Cumulative budgeted cost of the project

A

tracking chart that illustrated the expected budget expenditures by plotting the cumulative budgeted cost of the project against the baseline schedule