Chapter 6 Flashcards
includes processes required to manage the timely completion of the project.
Project Schedule Management
the process of establishing he policies/procedures and documentation for planning, developing, managing, executing, and controlling the project schedule
Plan Schedule Management
process of identifying and documenting the specific actions to be performed
Define Activities
process of identifying and documenting relationships among project activities
Sequence Activities
process of estimating number of work periods needed to complete individual activities with the estimated resources
Estimate Activity Duration
the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitor and controlling.
Develop Schedule
Two types of scheduling methods
Critical path or agile approach
Iterative scheduling with backlog
Type of rolling wave plan based on adaptive life cycles
typically uses kanban systems, based on a theory of constraints and pull-based schedule concepts from lean manufacturing to limit a team’s work in progress in order to balance demand against the team’s delivery throughput.
On-Demand Scheduling
Tailoring the schedule
- Life cycle approach
- resource availability
- project dimensions
- technological support
shorter life cycles providing rapid feedback on sustainability of deliverables and generally manifest as iterative schedule on-demand, pull-based schedule
Adaptive approaches
Defines summary milestones schedule that will influence/manage the product schedule.
Project Charter
Release and iteration length
using adaptive life cycle: time boxed periods for releases; waves and iterations are specified.
durations during which the team works steadily toward completion of a goal. Helps to minimize scope creep as it forces teams to process essential features first, then other features as time permits.
Time-Boxed Periods
specifies level of acceptance range used in determining realistic activity durations estimates and may include an amount for contingency
Level of accuracy
variance threshold for monitored schedule performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken.
Control Thresholds
Schedule management Tools & Techniques
- Expert Judgement
- Decomposition
- Rolling wave planning
- Meetings
defines activity process, defines final outputs as activities rather than deliverables
Decomposition
ITerative planning technique which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at higher levels.
Rolling wave planning
Includes activity identifier and scope of work description for each activity in sufficient detail to ensure work description for each activity in sufficient detail for understanding
Activity lists
Activity Attributes- Initial Stage
- include unique activity identifier (ID), WBS ID, and activity label or name
_________have zero duration because they represent a specific point of event.
Milestone List
Used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Diagramming method (PMD)
4 types of dependencies or logical relationships
Finish-to start (FS)- successor activity cannot start until a predecessor activity has finished. * Most Common
Finish-to-Finish (FF)- A successor activity cannot be finished until a predecessor activity has finished.
Start to Start (SS)- Activity cannot start until predecessor activity ends.
Start to finish (SF)- activity cannot finish until a successor activity has started * Rare
True or false: Two activities can have two logical relationships at the same time.
True- but not recommended between same activity.
Select relationships with the highest ________
Impact
_________are not recommended in logical relations.
Closed Loops
Dependency determination & Integration: characterized by attributes:
- Mandatory or discretional.
- Internal or external
The 4 attributes of dependency, 2 can by applicable at the same time.
Mandatory external dependence
Mandatory internal dependence
Discretionary dependencies
Discretionary dependencies.
Legally or contractually required or inherent in the nature of work. Involves physical limitations. Referred to as hard logic or hard dependencies. Determined by the team during the process of sequencing the activities
Mandatory Dependencies
Referred to as preferred logic, preferential logic, or soft logic. Establish based on knowledge of best practices within an application area or unusual aspect of the project where sequence is desired. Fully document as they can create arbitrary float values and can limit later scheduling options.
Discretionary Dependencies