Chapter 3.3 Flashcards

1
Q

Name 3 reasons why specifications may fall short of the standard needed

A
  1. Senior staff are not always given the training to write a specification
  2. Drafting or reviewing specifications can fall to more junior employees who have little or no experience of specifications and the context in which they are written
  3. Lack of information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When do under specified needs occur?

A

When not all of the users have been identified and so not all of the requirements have been identified and assessed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name the 4 main risks involved in an under specified need

A
  1. The product or service being procured is unsuitable to meet user needs
  2. Money is wasted either from having to rectify the product or service or from having to procure an alternative that does meet user needs
  3. Customer need is not fully satisfied and so the product or service is not used to its full potential
  4. If the specification is too narrow because the needs have been underspecified this can result in fewer alternatives with the result that costs can be higher because it is difficult if not impossible to switch to a lower cost product
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name 4 risks involved in an over specified need

A
  1. Greater expense because the product/service has to incorporate more features
  2. Poor competition because the number of suppliers who can provide the full specification is fewer than if the specification had not been over specified
  3. Variety of offers, most of which only provide some of the features specified, and few offers that are able to supply the full range of features
  4. More difficult to evaluate because there are more trade offs to be made between the different features and attributes in the specification
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name 3 problems of the user or supplier misinterpreting the need in the specification

A
  1. Unacceptable purchase that does not meet the standard of the user
  2. Time overrun as the product/service has to be adapted to meet the emerging real needs
  3. Increased costs from re-work to adapt the product/service to the real need
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name the 4 steps in the process of managing risk

A
  1. Identify the possible risks
  2. Assess the risks
  3. Control the risks
  4. Monitor the risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name 7 risks when producing a specification

A
  1. Insufficient funding delaying the procurement or even requiring a re-tender
  2. Timescales for tendering that are impractical
  3. Insufficient market research resulting in not all potential suppliers being identified and invited to bid
  4. Choosing an inappropriate procurement method
  5. Using terms and conditions that are not acceptable to suppliers
  6. Perceived bias or lack of confidentiality from the procurement team
  7. No response from suppliers who are known to be capable of providing a quality product or service
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

For every risk that is identified, what three things do the team need to establish?

A
  1. The impact of the risk if it was to occur
  2. The likelihood of the risk being detected before it causes any damage
  3. The likelihood of the risk being eliminated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define mitigating actions

A

Actions taken to lessen the impact of risk to people or organisations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the next step in managing risks

A

Controlling the risks by identifying any mitigating actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name the 4 main ways to mitigate risks

A
  1. Tolerate the risk
  2. Treat the risk
  3. Transfer the risk
  4. Terminate the risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should you consider before thinking about terminating a risk

A

You should consider rethinking the specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Name Spradlin’s 4 step process to problem solving when rethinking a specification

A
  1. Establish the need for a solution
  2. Justify the need
  3. Contextualise the problem
  4. Write the problem statement that describes the problem for which a solution is required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is normally used to monitor risks?

A

A risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Name 7 things a risk register should identify for each risk

A
  1. Unique identifier for each risk
  2. Date the risk was identified
  3. Allocated owner of the risk
  4. Description of the risk
  5. RAG assessment of the risk
  6. Mitigation action for the risk
  7. Date the risk will next be reviewed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does identifying the ownership of the risk do?

A

Help to ensure accountability

17
Q

Who may take a lead role in monitoring and reviewing specifications

A

Procurement

18
Q

Name 4 reasons why it is important to monitor and review specifications

A
  1. Accountability
  2. More focus on the goals of the specification
  3. Learning from experience
  4. Team morale
19
Q

What is the first step in monitoring and reviewing the creation of a specification by others?

A

Define success in terms of a completed specification

20
Q

What does PID stand for?

A

Project initiation document

21
Q

Define project initiation document

A

Document that outlines key elements of a project

22
Q

What does the project mandate do?

A

Explains the scope and authority of the project manager to commence project preparation activties

23
Q

What is the purpose of a project initiation document?

A

To document the key parts of the project for reference and act as a vehicle for collecting the necessary approvals

24
Q

Define project mandate

A

Document that authorises the project manager to commence with the project preparation

25
Q

Define opportunity cost

A

The potential benefits foregone as a result of choosing one alternative over another

26
Q

Name 11 things a PID will typically do

A
  1. Provide a background to the specification
  2. Provide the initial definition and scope of the specification
  3. Detail any constraints or dependencies
  4. List any assumptions
  5. Provide an outline business case for the specification
  6. Identify the benefits expected from the specification
  7. Provide roles and responsibilities for all those involved in writing or approving the specification
  8. Provide a stakeholder map
  9. Provide a communication plan
  10. List the acceptance criteria for the specification
  11. Include a project plan for completing the specification and the date on which it is due
27
Q

Name 3 popular metrics for managing projects

A
  1. Schedule variance - measures how far through the activities required by the plan in the PID the team is and by how much the plan is behind or infront of schedule
  2. Cost variance - measures how much time is expended by individuals versus the initial estimate of their involvement
  3. Stakeholder satisfaction - it could involve asking stakeholders to complete an online survey
28
Q

What may happen if progress in specification writing is monitored and reviewed too often?

A

Those involved can lose interest and motivation if they think they are being micro-managed

29
Q

What may happen if progress in specification writing isn’t monitored and reviewed enough?

A

It may lead to important events being missed with the overall effect being that the due date for the specification is missed

30
Q

How is best to monitor and review projects

A

Having regular meetings with the project team

31
Q

Name 7 steps for monitoring and reviewing a specification writing project

A
  1. Make sure the project is monitored throughout its lifecycle
  2. Decide what to measure and collect the right data
  3. Assign responsibility for reporting data and for monitoring it
  4. Identify who should receive monitoring reports
  5. Make strong and time bound decisions
  6. Have open and clear communication
  7. Make an effort to focus on people