Chapter 3 master scheduling Flashcards

1
Q
  1. After production planning the next step in the manufacturing planning and control process is to prepare…
A

Master production schedule MPS; What manufacturing will actually build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Master scheduling: master production schedule is the basis for communications between…
A

sales and manufacturing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Master scheduling:MPS is the priority plan for
A

Manufacturing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Master scheduling: MPS drives the
A

Material requirements plan; basis for calculating capacity and resources necessary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Master scheduling: Developing a master production schedule MPS; the objectives of the MPS?
A
  1. To maintain the desired level of customer service by maintaining inventory levels to meet customer requirements
  2. To make the best use of material, labor, and equipment
    3 to maintain inventory investment at the required levels
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Master scheduling: Developing a master production schedule MPS; Three steps in preparing the MPS
A
  1. Develop preliminary MPS
  2. Check the Preliminary MPS against the available capacity
  3. Resolve differences between the preliminary MPS and the capacity available
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Master scheduling: Developing a master production schedule MPS; Once the preliminary master production schedules are made they must be checked against available capacity. This process is called?
A

Rough-cut capacity planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Master scheduling: Developing a master production schedule MPS; rough-cut capacity planning checks for…
A

availability of critical resources such as operations, labor, and materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Master scheduling: Developing a master production schedule MPS; rough-cut capacity planning; is the available capacity…
A

Greater than the required capacity; adjustments may have to be made in overtime, labor, or equipment to meet customer needs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Master scheduling: Developing a master production schedule MPS; The MPS must be judged by three criteria…
A
  1. Resource use
  2. Customer service
  3. Cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Master scheduling: Developing a master production schedule MPS; Master schedule decisions; the MPS should represent as clearly as possible what…
A

manufacturing will make;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Master scheduling: Developing a master production schedule MPS; Planning horizon Is the…
A

Time spent for which plans are made; a period equal to the time required to accomplish the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Master scheduling: Production planning, master scheduling, and sales; the production plan reconciles the…
A

Total forecast demand with available resources;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. master scheduling: Production planning, master scheduling, and sales;MPS is a plan for ….
A

What production can do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. master scheduling: Production planning, master scheduling, and sales Available to promise
A

ATP is that portion of a firm’s inventory that is planned production that is not already committed and is available to the customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

50 Master scheduling:The MPS and delivery promises; The ATP is calculated by adding

A

Scheduled receipt to the beginning inventory and subtracting actual orders

17
Q

52 Master scheduling:Production planning, master scheduling, and sales; Projected available balance; The demand time fence

A

The demand time fence is the number of periods beginning with. One in which changes are not accepted due to excessive cost caused by schedule distribution

18
Q

52 Master scheduling:Production planning, master scheduling, and sales; Projected available balance; For periods Before the demand time fence the PAB is calculated as

A

Prior PERIOD PAB or on hand balance + the MPS - customer orders; This process ignores the forecast and assumes that the only effect will be from customer orders.

19
Q

52 Master scheduling:Production planning, master scheduling, and sales; Projected available balance; For periods AFTER the demand time fence the PAB is calculated Using

A

For periods after the demand time fence the PAB is calculated using the forecast or customer orders whichever is greater

PAB = prior. PAB + MPS - greater of customer orders or the forecast

20
Q

54 Master scheduling:Production planning, master scheduling, and sales; Projected available balance; What are the three time fences?

A
  1. Frozen zone
  2. Slushy zone
  3. Liquid zone
21
Q

54 Master scheduling:Production planning, master scheduling, and sales; Projected available balance; Frozen zone

A

In the frozen zone capacity and materials are committed to specific orders; changes would result in excessive costs

22
Q

53 Master scheduling:Production planning, master scheduling, and sales; Projected available balance; Slushy zone

A

In the slushy zone, capacity and materials are committed in a lesser extent in this area trade-offs can be negotiated between marketing and manufacturing