is the dominant mode in passenger travel and one of the principal freight modes. The U.S. highway system comprises approximately 3.9 million miles of highways
Highway transportation
the road building process includes:
- Planning (6 to 24 months)
- Design (15 to 24 months)
- Environment (9 to 36 months)
- Right-of-Way (6 to 21 months)
- Construction (12 to 36 months)
Thus, total project time can range from 4 to 12 years
The Wisconsin Department of Transportation follows a six-step process
- Select Project
- Investigate Alternatives
- Obtain Final Approvals
- Develop Project Design
- Prepare for Construction
- Construct the Project
is a high-capacity urban road that sits below freeways/motorways on the road hierarchy in terms of traffic flow and speed.
arterial road or arterial thoroughfare
is a low-to-moderate-capacity road which serves to move traffic from local streets to arterial roads.
collector road or distributor road
primarily serve as access roads to farms, residences, businesses and other abutting properties. They distribute traffic to highways in the higher functional classification network.
Local roads and streets
Intercity bus service is usually provided by private companies
True
Most vehicles registered as trucks are less than 10,000 lbs in gross weight, and over half of these are used for personal transportation.
True
DOT
Department of Transportation