Chapter 14 - Advanced Variance Analysis Flashcards

1
Q

What are planning and operational variances

A

Planning variances are the classification of variance is calculated by comparing the original budget to the budget revise for any permanent changes to be more realistic budget

Operational variances is a classification of variances calculate by comparing actual performance with revised budget these variances are worth investigating more as they are parents is caused by operating factors that potentially might be controllable

Planning an operational variances in essence takes the variance analysis already done and tries to separate it to what are permanent changes (planning variance) such as supplier increasing cost of raw materials versus operational variances which are attributed to decisions made within the company for example buying cheaper materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How to use planning an operational variances in a question

A

It is pretty simple. Take expenditure variance let’s say originally we expected $5 per kilo And we actually spent $4.75 per kilo on 108,000 kg. If this is all the question states then you can see that we are favourable by $.25 per kilo however the question says since the preparation of the budget the prices change to $4.85.

Therefore to work out the planning variance (permanent changes) saving Of $.15 per kilo are due to changes in the price ($5 to $4.85) therefore 108,000 x .15 = £16,200 of the overall 27,000 favourability is accounted for with planning

Operational variance (how good or bad the manager is at his job) in this occasion is $.10 because we paid $4.75 and we should’ve paid $4.85 therefore the variance for operational is $10,800.

As you can see here we have split out the original 20,000 favourability and see what is market trends and what is efficiency within the company in terms of buying things

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are mix and yield variances

A

Mix variance-this shows the effect of changing the proportions of the mix of materials input into the process for example if we are making a smoothie if we use less strawberry then we need to use more banana to ensure that the total Litre is the same

Yield variance – This shows the difference between the actual unexpected output or yield from the process (for example lost materials due to evaporation) 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How to calculate the mix variance

A

Create a table that shows both products with the materials unit price and total. This is how much we actually spent on the mix and then look at how Much materials we actually Spence and workouts what the ratio should’ve been for example if the total materials used was 3000 and material x used 2 kg and material y used 1 kg then we would expect material x to be 2000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How to work out the yield variance

A

This variance is in regards to things such as evaporation so we need to look at the total units used and the total cost versus the actual production time is the standard cost. For example if both X and y used 15200kg but production was 5000 (x used 2 kg and y uses 1 kg) then we know it should have been 15000 in total so overused by 200kg @ std cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How to workout the usage variance for mix And yield

A

Add the mix variance and yield variance together to give the usage variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are some other mix variances

A

 Sales price variance

Sales volume variance

Sales mix variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Sales price variance

A

Take the actual sales and the actual price per unit and take the actual sales on the porch is the price per unit and see the difference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How to work out the sales Mix variance

A

Let’s say we have three products A and B and actual sales were 180 for A, and 120 for B however we were expecting the sales mix to be 100 of A and 50 of B so we know that 2/3 should have been A. Add together the sales = 300 and find 2/3 to get 200 the difference of 100 @ std cost is the mix variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Sales volume variance

A

Actual sales standard profits versus budget sales at standard profits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the quantity variance

A

Actual total unit at standard price vs budget total units at standard price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do these new sales variances tie in to chapter 13

A

Remember in the last chapter the sales variance is either sales price or sales volume. Sales volume can be split into sales mix and quantity variance because if you think about it the total sales that we make versus budget would differ because either the quantity was difference e.g. we sell more which is the quantity variance for the mixture of sales is difference which is the sales mix variance. For example if we budgeted to sell 100 units of product a for $6 and 100 units product b for $1 but we actually sold 150 of product a and 50 of product b though the totals are the same the mix is different

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How to work out the sales volume variance without any information

A

The sales volume as it is split into the sales mix and sales quantity variance if you add these variances together it will give you the volume variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly