Chapter 14 Flashcards

1
Q

A temporary endeavor undertaken to create a unique product, service, or result. Clear starting and ending point. (A unique undertaking by the company)

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The application of knowledge, skills, tools and techniques to project activities to meet project requirements.

A

Project management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

5 project phases

A
Concept 
Project definition 
Planning 
Performance 
Postcompletion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Here, project planners develop a broad definition of what the project is and what it’s scope will be (idea for what the project should be)

A

Concept phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Setting boundaries for what is involved in your project is called the

A

Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Here, project planners identify how to accomplish the work, how to organize for the project, the key personnel and resources required to support the project, tentative schedules, and tentative budget requirements

A

Project definition phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Here, project planners prepare detailed plans that identify activities, time and budget targets, and the resources needed to complete each task. Also includes putting in place the organization that will carry out the project.

A

Planning phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A performance or time target for each major group of activities in a project

A

Milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In this phase, the organization actually starts to execute the project plan

A

Performance phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

This is the phase in which the project manager or team confirms the final outcome, conducts a post implementation meeting to critique the project and personnel, and reassigns project personnel

A

Postcompletion phase (what went well and what went wrong)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Horizontal bar chart. Graphical tool used to show expected start and end times for project activities and to track actual process against these time targets

A

Gantt chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A graphical tool that shows the logical linkages between activities in a product

A

Network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A network based technique in which there is a single time estimate for each activity

A

Critical path method (CPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A network-based technique in which there are multiple time estimates for each activity

A

Program evaluation and review technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A project activity for which the earliest start time and latest start time are equal (zero slack). This cannot be delayed without lengthening the overall project duration.

A

Critical activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The determination of the earliest start and finish times for each project activity

A

Forward pass

17
Q

The earliest an activity can start, as determined by the earliest finish time for all immediate predecessors

A

Earliest start

18
Q

The earliest an activity can finish, calculated by adding the activity’s duration to its earliest start time

A

Earliest finish

19
Q

The determination of the latest finish and start times for each project activity

A

Backward pass

20
Q

The latest an activity can finish and still finish the project on time, as determined by the latest start time for all immediate successors (what came after it)

A

Latest finish

21
Q

The latest an activity can start and still finish the project on time, calculated by subtracting the activity’s duration from its latest finish time

A

Latest start

22
Q

The difference between an activity’s late start and early start time it between the late finish and early finish times. The amount of leeway you have for starting an activity.

A

Slack

23
Q

The critical path does not have what

A

Slack

24
Q

Shortening the overall duration of a project by reducing the time it takes to perform certain activities

A

Crashing

25
Q

Crash cost per period formula

A

(CC-NC)/(NT-CT)