  1. Goals of a pre-job conference include:
A
  • Discus HSE requirements
  • Address/clarify emergency procedures
  • Review and discuss scope of work (SOW)
  • Review logistical support
  • Discuss line communications between parties
  • Review known critical hazards
  • Establish list of critical points of contact (POC)
  • Discuss and clarify inspector(s) responsibilities and authority
  • Clarify the chain of command (reporting system)
  • Discuss and clarify areas of concern in the project specification (omissions, clarifications, testing)
  • Agree on critical hold points for inspections
  • Agree on method of conflict resolution between the inspector and applicator
  • Agree on procedures for change orders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. People who may be required to attend a pre-job conference include:
A
  • Owner
  • Owner’s contract manager
  • Engineer
  • Specifying engineer
  • Operations personnel
  • Specifier
  • Purchasing agents
  • Coating manufacturer
  • Coating inspector(s)
  • Project safety personnel
  • Coatings applicator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Before the start of the pre-job conference the inspector should obtain a copy of, read, and understand the:
A
  • Specification
  • Standard/procedure referenced in the project specification
  • Manufacturers’ product data sheets
  • Safety requirements of the SDS
How well did you know this?