Chapter 13: Discharge Flashcards
1 Introduction to Discharge
Every contractual obligation gives rise to a corresponding contractual right. Where the obligation of one party is discharged, the corresponding right of the other party is extinguished. Where all obligations arising under a contract are discharged and all rights thus extinguished, the contract is discharged.
A contract might be discharged in one of the following ways:
(a) Performance;
(b) Expiry;
(c) Agreement;
(d) Breach; or
(e) Frustration.
You will consider each of these in turn.
2 Discharge by expiry and by performance
2.1 Discharge by expiry: A contract will expire when it is completed according to its own terms. Contract expiration is often by date ie the parties incorporate a term in the contract which stipulates when the contract comes to an end. For example, the contract provides that the contract will expire 12 months after
the commencement date. A contract can also expire based on the occurrence of an event. For example, a contract may include a term that the supplier is to deliver goods to the buyer within a given time frame and upon delivery the contract comes to an end.
2.2 Discharge by performance
2.2.1 The entire obligations rule: A contractual obligation is discharged by a complete performance of the obligation. The promisee is entitled to the benefit of complete performance exactly according to the promisor’s ‘undertaking’. A promisor who only performs part of their obligation is not discharged from that obligation.
Imagine that a contract provides that A will pay B after B has performed its obligations (such as
providing a service). B cannot bring a claim for the payment until performance is entirely complete. Nor, as a general rule, can B bring a claim for half of the payment when it has provided half the service, even if half the service is of value to the other party. B has to entirely complete performance, and then it is entitled to the entire payment
Key case: Cutter v Powell (1796) 6 Term Rep 320
Facts: Cutter agreed to serve on a ship from Jamaica to Liverpool. The defendant, Powell, agreed
in return to pay Cutter 30 guineas (which was four times the going rate) ‘provided he proceeds,
continues and does his duty […] from hence to the port of Liverpool’. Cutter died at sea some
seven weeks into the voyage and nineteen days short of Liverpool. Cutter’s widow brought an
action to recover a proportion of the agreed contract price.
Held: the action failed. The contract was said to be entire. Cutter was obliged to perform the
given duty fully before he could demand payment. As the contract had not been completely
performed the widow was entitled to nothing.
2.2.2 Exceptions to the entire obligations rule: Acceptance of partial performance
Where one party has given only partial performance of the contractual obligations, it is possible
that the innocent party, rather than reject the work done, might accept that part of the
performance. However, it should be noted that such an acceptance of partial performance is at
the discretion of the innocent party. If the innocent party voluntarily accepts partial performance,
then the party in default will be entitled to payment on a quantum meruit basis.
Quantum meruit (meaning as much as is deserved) is a remedy whereby the claimant may be able to claim a reasonable sum so that the defendant is not unjustly enriched. The court will assess the value of a
quantum meruit award on an objective basis using the information available to it, for example the
usual market price for goods or services
Sumpter v Hedges (1898) 1 QB 673
Sumpter had agreed to build two houses with stables on Hedges’ land, in return for a fixed price. After completing work worth around half of the contract
price, Sumpter told Hedges that he did not have enough money to finish the job, so Hedges did it
for himself.
Since the work had been done on the innocent party’s land, the court felt that the innocent party had no choice but to complete the work. He was in possession of what he could not fail to keep. This was not voluntary acceptance of partial performance as the innocent party did not have the option to take or not to take the benefit of the work done.
If the court had found otherwise, however, the builder would have been entitled to a quantum meruit to compensate him for the value of the work done. In the event, he was entitled to compensation for the value of the materials which he had left on site which had not been incorporated into the
building which the innocent party used to complete the work. This was because the innocent
party had the choice as to whether or not to use these, as they could have been returned.
Substantial performance: Defect
Where a contract has been substantially performed, it may be possible for the party who rendered such substantial performance to obtain the contract price subject to a deduction to reflect the cost of remedying the ‘defect’ (ie the aspect which has not been performed).
When considering such a plea, the court considers the nature and extent of the defect, which is done by
measuring the cost of remedying the defect against the contract price. If the defect is too serious,
the party who rendered the defective performance will not be entitled to recover any money.
However, if substantial performance is found to have been rendered, then the party will be entitled
to the contract price subject to a deduction.
In defining what is ‘substantial performance’, the court takes a similar approach to when deciding
whether has been a repudiatory breach of contract: the question is whether the defect goes ‘to
the root of the contract’.
Hoenig v Isaacs [1952] 2 ALL ER 176
Hoenig agreed to redecorate completely and refurnish Isaacs’ one bedroom flat. Hoenig finished the work, but the job had some defects which would
require further attention eg the wardrobe he fitted needed a new door, and the built in bookcase
was slightly too short for the space. The total value of the work was around £750, and the repairs
would cost around £55. Hoenig sued for payment but admitted that Isaacs was entitled to reduce
the payment to reflect the cost of repairs. Isaacs said that entire performance was a condition
precedent to any payment, and therefore, following Sumpter, he only had to pay a quantum
meruit (in return for taking the benefit of the work)
Hoenig v Isaacs [1952] 2 ALL ER 176 Judgement
The court held in this case, the contract had been substantially performed, and all that was left
were ‘defects and omissions’. These did not go to the root of the contract. Hoenig was therefore
entitled to the contract price, less a deduction for the defects (probably calculated as the cost of
remedying the defects).
Bolton v Mahadeva [1972] 1
WLR 1009
The claimant undertook to install a central heating system in the defendant’s house at
a cost of £560. The system did not work, and the defendant refused to pay any money. The cost
of remedying the defects would have been £174. The court had to determine whether the claimant
was entitled to recover any payment under the contract.
Bolton v Mahadeva [1972] 1
WLR 1009 Judgement
It was held that whether or not the contract had been substantially performed should be viewed
with regard to the purpose of the contract and the circumstances as a whole. The purpose of the
contract in this case was to install a central heating system to heat a house. If that system did not
function adequately and moreover produced harmful fumes, then it was not possible to say that the contract had been substantially performed. Accordingly, the claimant was not entitled to
recover any of the contract price but, had he offered to remedy the defects, and had then done
so, he would be justified in claiming the contract price.
Divisible obligations
Some contracts are clearly intended to be divided into parts, eg the payment of a salary under a
fixed contract of employment. If this is the case, then the performing party is entitled to payment
for each part which is performed. However, the question as to whether a contract is divisible or
entire depends upon the intention of the parties.
Wrongful prevention of performance
Where one party performs part of the agreed obligation, and is then prevented from completing
the rest by some fault of the other party, they will be entitled to payment despite not having
completed the rest of the obligation (Planche v Colborn (1831) 131 ER 305). The innocent party has
two options:
(a) To sue for damages for breach of contract; or
(b) To claim a quantum meruit.
2.2.3 Defences to allegations of failure to perform
Tender of performance:
In an action for breach of contract for failing to perform an obligation, it is a good defence for the
defendant to show that they ‘tendered performance’. In order for a plea of tender to be successful, the promisor must show that they unconditionally offered to perform their obligations in accordance with the terms of the contract, but that the promisee refused to accept such performance.
For instance, if the seller delivered goods but the purchaser refused to accept delivery, the seller would be relieved of liability for failing to deliver. In relation to payment of a debt, a plea of tender does not discharge the debt. However, it would prevent the creditor from claiming interest or damages on that debt subsequent to the tender of performance.
2.3 Summary
- A contract will expire when it is completed according to its own terms. Contract expiration is
often by date but a contract can also expire based on the occurrence of an event. - Generally, an obligation is discharged by complete performance of the obligation. Until the
obligation is completely performed, the performing party is not entitled to payment. There are
four key exceptions: - If one party accepts partial performance, the other party is entitled to payment for the
partial performance on a ‘quantum meruit’ (as much as is deserved) basis; - If one party has substantially performed the contract, they may be entitled to the contract
price subject to a deduction for the cost of remedying the defect; - Some contracts are divisible, and a party is entitled to payment for each part. This turns on
the intention of the parties; - Where a party is prevented from completing performance by the other party’s default, they
can sue for damages for breach of contract or claim a quantum meruit.
3 Discharge by agreement
3.1 Introduction
On the basis that something may be destroyed in the same manner by which it was created, a
contractual obligation may be discharged by agreement. This may occur in one of two ways:
(a) By a subsequent binding contract between the parties; or
(b) Alternatively, by operation of a term of the original contract.
3.2 Discharge by subsequent binding contract
The essence of this concept is the formation of a new contract, and this may occur in several
ways.
1) New Contract to Waive Rights of old Contract: For instance, where both parties have obligations which remain unperformed, the contract may
be discharged by mutual waiver. This is a new contract by which each party agrees to waive their
rights under the old contract in consideration for being released from their obligations under the
old contract.
Also known as Termination Agreement: This type of arrangement is very common in commercial situations where parties wish to end an existing contract and achieve commercial certainty. They will often agree the terms of a termination agreement to release and settle any liabilities under the original contract so that they can be sure that they will have no further liabilities or obligations arising from it in the future.
Accord & Satisfaction
Accord (A agrees to release B from its obligations
under the old contract.)
Satisfaction (B agrees to release A from its obligations
under the old contract)
For this discharge to be effective, two elements must be present, sometimes called ‘accord and
satisfaction’: there must be agreement that the obligation will be released (‘accord’), and there
must be consideration for the promise to release a party from the obligation (‘satisfaction’).
Difficulties relating to necessities
Accord (A agrees to release B from its obligations
under the old contract)
Satisfaction (Arguably there is no satisfaction. B cannot meaningfully agree to release A from its
obligations under the old contract, because A
has already performed those obligations)
Where one party has performed its obligations in their entirety but something remains to be done by the other party.
Agreement Under Deed
One way of resolving this issue is that the party to whom the obligation is owed may release the
other party by a subsequent agreement under deed. This avoids the need for consideration
altogether, because a gratuitous promise (one without any consideration) is enforceable if made
in a contract in the form of a deed.
There is no need for accord and satisfaction when a party is released from an obligation by
deed.
Accepting something different in place of former obligations
Accord (A agrees to release B from its obligations
under the old contract)
Satisfaction (B agrees to accept a new and different
obligation to the existing obligation – such as
paying instalments earlier)
Alternatively, the party to whom the obligation is owed may provide consideration by agreeing
with the other party to accept something different in place of the former obligation, for example
the accelerated payment of a sum payable in instalments:
Key point on accord & satisfaction
Where there has been accord and satisfaction, the former obligation is discharged. The essential
point is that, unless there is a new consideration, there can be no satisfaction, ie there can be no
discharge of the previous agreement and no formation of an agreement on new terms.
3.3 Discharge by the operation of a term in the contract
There is no reason why a contract should not contain a term providing for the discharge of
obligations arising from the contract. Such a term may be either a condition precedent or a
condition subsequent.
3.3.1 Condition precedent
A condition precedent is a condition which must be satisfied before any rights come into existence. Where the coming into existence of a contract is subject to the occurrence of a specific event, the contract is said to be subject to a condition precedent. The contract is suspended until
the condition is satisfied. Where a condition precedent is not fulfilled, there is no true discharge
because the rights and obligations under the contract were contingent upon an event which did not occur, ie the rights and obligations never came into existence in the first place.
Example of condition precedent
Certain companies are required by law to obtain approval from shareholders before carrying out
high value contracts. When agreeing the high value contract, the company could include a clause
stipulating that it is a ‘condition precedent’ of the contract that approval is provided by the shareholders. Until that approval is provided, the remaining rights and obligations in the contract
are not binding. If the shareholders refuse to provide the approval, then the contract never becomes binding, and the company does not infringe the law which prevents the high-value contract.
3.3.2 Condition subsequent
A condition is subsequent is a term providing for the termination of the contract and the discharge
of obligations outstanding under the contract, in the event of a specified occurrence. Condition subsequent: A condition which, if satisfied, releases a party from binding obligations.
3.4 Summary
- The parties can discharge a contract by agreeing to do so in a subsequent binding contract.
- For this to happen, the new contract needs to be supported by consideration (unless it is
effected by deed). Particular care needs to be taken where one party has performed the
old contract in full, in which case being released from it will not be good consideration. - A contract can include terms providing its own discharge:
- A ‘condition precedent’ is a condition that must be satisfied before any rights come into
existence. This is not discharging a contract in the strict sense, it is preventing it from
becoming binding in the first place. - A ‘condition subsequent’ is a term providing for the termination of the contract and the
discharge of obligations outstanding under the contract upon the happening of a specific
event.
4 Discharge by breach
4.1 Repudiatory breach of contract at common law: The usual remedy for breach of contract is an award of compensatory damages, ie monetary compensation. Such a remedy is in principle available for any breach of contract, but a party does not always acquire a right to terminate the contract as a result of a breach of contract.
However, in certain circumstances, the innocent party may, in addition, treat the contract as having been terminated for repudiatory breach. This is where one party has breached a term of the contract which is either a condition or an innominate term which is to be treated as a condition. The distinction between conditions and innominate terms is not addressed in this section.
The consequences of a breach of contract
- Identify breach and categorise the term breach
- Breach of warranty (or innmominate term treated as such) = Damages only
- Breach of condition (or innominate term treated as such) = Damages plus right of election
Termination for repudiatory breach is therefore one way in which a contract may come to an end. Generally, where there has been a repudiatory breach, a party has a choice as to whether to
terminate the contract or to affirm it (keep it in place). The choice is not entirely unrestricted. We
will consider the effect of termination before considering this choice
4.2 Anticipatory breach
It is important to note at this stage a particular type of breach of contract known as ‘anticipatory
breach’. This is where a party indicates they will not perform their contractual obligations in advance of the date for performance. A party who, by words or conduct, leads a reasonable person to conclude that they do not intend to perform their part of the contract, is said to have ‘renounced’ the contract. The innocent party has an immediate right to ‘accept’ the renunciation and to treat the contract as terminated (Hochster v De la Tour (1853) 2 E&B 678).
Performance of contractual obligations
An indication by a party that he will not perform their contractual obligations in only a minor regard will not give rise to the right to terminate. If a party wants to rely on an anticipatory repudiatory breach to terminate the contract then it will need to demonstrate that if the breach occurred at the time performance was due it would have been repudiatory.
Repudiatory breach: Where one party has breached a term of the contract which is either a
condition, or an innominate term which is treated as a condition, entitling the other party (in
principle) to treat the contract as terminated.
Anticipatory breach: Where a party indicates they will not perform their contractual
obligations in advance of the date for performance.
4.3 What is the effect of terminating a contract for repudiatory breach?
Claim of damages: Where the contract is terminated following a repudiatory breach this puts an end to all primary obligations of both parties remaining unperformed. Furthermore, the innocent party can claim damages not only arising from the specific breach but also the loss of the contract caused by the
termination of the contract as a whole.