Chapter 12 - Outside Plant Flashcards

1
Q

The ICT distribution designer should design conduits entering from:

  • Basement wall to terminate ~ ___ in from the finished wall
  • Below grade point to extend ~ ___ above finished floor (AFF)
  • Ceiling height to terminate ~ ____ below the finished ceiling
A

4 inches for these cases

Note: 4in penetration is specified for EFs, as opposed to the 1” to 3” penetration specified for intrabuilding conduit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The penetration specified for intrabuilding conduit is:

A

1in to 3in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the three locating methods?

A
  • Electronic :signal or tone is placed on utility and receiver detects signal and locates utility based on strength and distribution of radiated field
  • Water vacuum: If several layers of utilities are possible, and adequate identification is questionable this is used. Uses a special truck that uses high pressure water spray-vacuum. Also known as soft digging. System will excavate a small 6in wide hole to the desired spots along the routes
  • Air vacuum: sends high pressure supersonic air streams into porous soil. Does not damage utilities due to their impermeability. Hole has diameter of 6in to 10in and go go several feet vertically. Another method of soft digging.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A ___ interface is the connection between the access provider (AP) and a private network within a building.

A

Network interface

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the BICSI recommended wall length for terminating space for telecommunications entrance facilities serving up to the following gross floor spaces?

10,000 sq ft
20,000 sq ft
40,000 sq ft
50,000 sq ft
60,000 sq ft
80,000 sq ft
100,000 sq ft
A
10,000 sq ft = 39ft
20,000 sq ft = 42ft
40,000 sq ft = 68ft 
50,000 sq ft = 90 ft
60,000 sq ft = 95ft
80,000 sq ft = 120ft
100,000 sq ft = 144ft
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

All hardware in manholes must be galvanized. MHs should be equipped with:

A
  • sump pump of at least 13in diameter
  • pulling eyes of at least 0.875in diameter
  • bonding and grounding provisions
  • entry ladder (where feasible)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The count level of service diversity assigns circuits:

A

among different binder groups or fiber tubes within one cable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The sheath or cable level of service diversity assign circuits:

A

among different sheaths or cables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The route level of service diversity assigns circuits:

A

among entirely different cable paths to a building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The backbone level of service diversity assign circuits:

A

among different intrabuilding backbone and cabling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If a maintenance hole (MH) is longer than ____, it should be equipped with three covers.

A

20ft

Use 2 covers if between 12ft and 20ft

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the minimum separation between communications conduit and direct buried power or other foreign conduit?

  • Of concrete?
  • of masonry?
  • of well-tamped earth?
A

3in of concrete
4 in of masonry
12in of well-tamped earth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the minimum separation between direct buried telecommunications conduit and pipes (gas, oil, water)?

A

6 in when crossing

12 in when parallel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the minimum separation between direct buried telecommunications conduit and street railways?

A

3.28ft below top of rail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the minimum separation of direct buried telecommunications conduit and railroads?

A

50in below top of rail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Trenches should be ____ or deeper, with a minimum clearance of ___ from edge of excavated dirt pile to nearest edge of trench.

A

5ft deep,
2ft clearance
Trench should also be shored, sloped, or stepped to prevent cave-in

17
Q

Terminating conduit at the property line, should have minimum cover depth of __ and prepare for tie-in connections.

A

Minimum cover depth of 24in

18
Q

Terminating service entrance conduit into the building should be at ___ below finished ceiling, or if coming in below grade to be ___ above finished floor.

A

4in below finished ceiling

4in above finished floor

19
Q

Limit OSP cabling aerial entrances to small buildings requiring what?

A
  • less than 300 pairs and 100ft or less in length

- no other telecommunications facility entrances

20
Q

When aerial entrances are used, the span from the last pole to the building must not exceed ____.

A

100ft

21
Q

The termination/transition for OSP cable may not exceed ____ from the point of entrance. Indoor/outdoor rated cables can be installed beyond this length from the point of entrance if approved by the AHJ.

A

50ft

22
Q

Building larger than ___ must contain a dedicated room for EFs.

A

100,000 sq ft

23
Q

Where posts and bollards are needed, they should be a minimum of ___ in diameter, filled with concrete, encased to a minimum depth of ___, and extend a minimum of ___AFF or ground level.

A

4in diameter
36in minimum depth
42in AFF

24
Q

Termination points for entrance facilities (EF) should enter from:

  • basement wall to terminate ___ from the finished wall
  • below grade point to extend ___ above finished floor (AFF)
  • ceiling height to terminate ___ below finished ceiling
A

4in for all cases.

Note: this is different than the 1in to 3in specified for intrabuilding conduit

25
Q

Pedestals should serve only single-story office or office warehouse structures and should be installed within ___ of each tenant space in buildings of this type of construction.

A

150 ft

26
Q

Surface mounted cabinets for outside building terminals should be at least:

___ tall
___ wide
___ deep

A

1m(3.28ft) tall
24in wide
6in deep