Chapter 11 Flashcards

1
Q

What is capital budgeting?

A
  • Analysis of potential additions to fixed assets
  • Long-term decisions; involve large expenditures
  • Very important to firm’s future
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Steps to Capital Budgeting

A
  1. Estimate CFs (inflows & outflows)
  2. Assess riskiness of CFs
  3. Determine the appropriate cost of capital
  4. Find NPV and/or IRR
  5. Accept if NPV > 0 and/or IRR > WACC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Independent Projects

A

If the cash flows of one are unaffected by the acceptance of the other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Mutually Exclusive Projects

A

If the cash flows of one can be adversely impacted by the acceptance of the other

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Normal Cash Flow Stream

A
  • Cost (negative CF) followed by a series of positive cash inflows
  • One change of signs

***Cost (negative CF), then string of positive CFs, then cost to close project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Nonnormal Cash Flow Stream

A

Two or more changes of signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Net Present Value (NPV)

A

Sum of the PVs of all cash inflows and outflows of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Rationale for the NPV Method

A

NPV= PV of inflows – Cost= Net gain in wealth

  • If projects are independent, accept if the project NPV > 0
  • If projects are mutually exclusive, accept project with the highest positive NPV, one that adds the most value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is a project’s IRR similar to a bond’s YTM?

A
  • They are the same thing

- Think of a bond as a project. The YTM on the bond would be the IRR of the “bond” project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Rationale for the IRR Method

A
  • If IRR > WACC, the project’s return exceeds its costs and there is some return left over to boost stockholders’ returns
  • If IRR > WACC, accept project
  • If IRR < WACC, reject project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Independent Projects (NPV/IRR)

A

NPV and IRR always lead to the same accept/reject decision for any given independent project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Finding the Crossover Rate

A
  • Find cash flow differences between the projects. See Slide 11-8
  • Enter the CFs in CFj register, then press IRR
  • If profiles don’t cross, one project dominates the other
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Reasons Why NPV Profiles Cross

A
  • Size (scale) differences: The smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so a high WACC favors small projects
  • Timing differences: The project with faster payback provides more CF in early years for reinvestment. If WACC is high, early CF especially good, NPVS > NPVL
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Reinvestment Rate Assumptions

A
  • NPV method assumes CFs are reinvested at the WACC
  • IRR method assumes CFs are reinvested at IRR
  • Assuming CFs are reinvested at the opportunity cost of capital is more realistic, so NPV method is the best. NPV method should be used to choose between mutually exclusive projects
  • Perhaps a hybrid of the IRR that assumes cost of capital reinvestment is needed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Managers prefer the IRR to the NPV method; is there a better IRR measure?

A
  • Yes, MIRR is the discount rate that causes the PV of a project’s terminal value (TV) to equal the PV of costs. TV is found by compounding inflows at WACC
  • MIRR assumes cash flows are reinvested at the WACC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why use MIRR versus IRR?

A
  • MIRR assumes reinvestment at the opportunity cost = WACC. MIRR also avoids the multiple IRR problem
  • Managers like rate of return comparisons, and MIRR is better for this than IRR
17
Q

What is the payback period?

A
  • The number of years required to recover a project’s cost, or “How long does it take to get our money back?”
  • Calculated by adding project’s cash inflows to its cost until the cumulative cash flow for the project turns positive
18
Q

Discounted Payback Period

A

Uses discounted cash flows rather than raw CFs

19
Q

Strengths of Payback

A
  • Provides an indication of a project’s risk and liquidity

- Easy to calculate and understand

20
Q

Weaknesses of Payback

A
  • Ignores the time value of money (TVM)
  • Ignores CFs occurring after the payback period
  • No relationship between a given payback and investor wealth maximization

***Discounted payback considers TVM, but other 2 flaws remain

21
Q

Why are there multiple IRRs?

A
  • At very low discount rates, the PV of CF2 is large and negative, so NPV < 0
  • At very high discount rates, the PV of both CF1and CF2 are low, so CF0 dominates and again NPV < 0
  • In between, the discount rate hits CF2 harder than CF1, so NPV > 0
22
Q

When to use the MIRR instead of the IRR?

A

When there are nonnormal CFs and more than one IRR, use MIRR