CH.8 Installing Sewer Systems Flashcards

1
Q

Municipal sewer system consists of:

A

laterals, mains that collect and transmit sewage to plant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Pressure Pipe

A

Must be laid to even falls and grades

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Gravity Pipe

A

Must be flow down hill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Pipe Diameter

A

when you double pipe diameter, carrying capacity increases 4 times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

slope

A

grade in pipe that causes a fluid to flow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Backfill

A

when a pipe is laid level or slopes the wrong way

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Pipe materials

A

cost, strength, ease of installation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Pipe Bedding

A

can reinforce pipe by providing support; resist flattening effect and provide firm base

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

pipe volume in cubic yards

A

D X D X .7854 X L (FEET) / 27

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Five most common sewer pipe materials

A

concrete, clay, DI, transite (AC), PVC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

fittings

A

used to change pipe size, pipe type or direction of flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

wye

A

allows service pipe to enter the main, provides cleanout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

roll-over gasket

A

used in concrete sewer pipe up to 10 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

gaskets

A

used to join bell and spigot of same material pipe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Equipment Needed

A

excavators, back fill equip.,hand tools, laser and optical levels, pumps.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

manholes

A
  1. change directions of lines

2. intersections of lines

17
Q

sections

A

precast manholes are usually 4-6’ in diameter and 1,2 or 3’ high.

18
Q

cone

A

top section of manhole

19
Q

base

A

bottom section

20
Q

testing

A
  1. visual
  2. mandrel
  3. water testing (infiltration and exfiltration)
  4. air test