Ch6.5 - Estimate Activity Duration Flashcards
Estimate Activity Durations
process of estimating the number of work periods needed to complete individual activities with estimated resources
Estimate Activity Durations Benefit
provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process
Inputs for Estimate Activity Durations(10)
EEF, OPA, Sched Mgmt Pln, Activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, risk register, resource breakdown structure
TT for Estimate Activity Durations (6)
expert judgement, analogous estimating, parametric estimating, three-pt estimating, group decision making techniques, reserve analysis
Outputs for Estimate Activity Durations (2)
activity duration estimates, project doc updates
Input for Estimate Activity Durations: Schedule Management Plan
defines the method used and the level of accuracy along with other criteria required to estimate activity durations including the project update cycle.
Input for Estimate Activity Durations: Activity List
activity list identifies the activities that will need duration estimates.
Input for Estimate Activity Durations: Activity Attributes
primary data input for use in estimating durations
Input for Estimate Activity Durations: Activity resource reqts
level to which the resources assigned to the activity meet the requirements will significantly influence the duration of most activities. For example, if additional or lower-skilled resources are assigned to an activity, there may be reduced efficiency or productivity due to increased communication, training, and coordination needs
Input for Estimate Activity Durations: Resource Calendars
resource calendars influence the duration of schedule activities due to the availability of specific resources, type of resources, and resources with specific attributes.
Input for Estimate Activity Durations: Project Scope Statement
assumptions and constraints from the project scope statement are considered when estimating the activity durations; Ex: Existing conditions,
Availability of information, and
Length of the reporting periods.
Input for Estimate Activity Durations: Risk Register
list of risks, along with the results of risk analysis and risk response planning.
Input for Estimate Activity Durations: Resource Breakdown Structure
provides a hierarchical structure of the identified resources by resource category and resource type.
Input for Estimate Activity Durations: Enterprise Environmental Factors
Duration estimating databases and other reference data,
Productivity metrics,
Published commercial information, and
Location of team members.
Input for Estimate Activity Durations: Organizational Process Assets
Historical duration information,
Project calendars,
Scheduling methodology, and
Lessons learned.