Ch6.0 - Schedule Management Flashcards
Project Time Management is what?
the processes required to manage the timely completion of the project.
What are 6 processes within Schedule Management
Plan Schedule Management Define Activities Sequence Activities Estimate Activity Durations Develop Schedule Control Schedule
How do we distinguish between the project schedule presentation from schedule data and calculations?
Refer to schedule model = schedule management plan. Identifies scheduling method and tool, format and critera for developing/controlling project schedule
Scheduling methods (2)
CPM and CCM
CPM
Critical Path Method
CCM
Critical Chain Method
The schedule management plan is a subsidiary plan of what?
The project management plan
What is the overall Project Schedule Plan approach
Scheduling method to scheduling tool to scheduling model to project schedule. Includes project information.
What is the overall Project Schedule Plan approach diagram