Ch4.4 - Monitor and Control Project Work Flashcards

1
Q

Monitor and Control Project Work

A

process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Monitor and Control Project Work Benefit

A

allows stakeholders to understand the current state of the project, the steps taken, and budget, schedule, and scope forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4-8 ITTO Monitor/Control Proj Work

A

4-8 ITTO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4-9 Monitor/Control Proj Work DFD

A

4-9 Monitor/Control Proj Work DFD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Whe is monitoring performed udring the project

A

Throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does monitoring include in terms of activities

A

collecting, measuring, and distributing performance information, and assessing measurements and trends to effect process improvements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does control include

A

determining corrective or preventive actions or replanning and following up on action plans to determine whether the actions taken resolved the performance issue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Monitor and Control is concerned with:

A
  1. Comparing actual project performance against the project management plan;
  2. Assessing performance and then recommending those actions as necessary;
  3. Identifying new risks and analyzing, tracking, and monitoring existing project risks ;
  4. Maintaining an accurate, timely information base concerning the project’s product(s) and their associated documentation through project completion;
  5. Providing information to support status reporting, progress measurement, and forecasting;
  6. Providing forecasts to update current cost and current schedule information;
  7. Monitoring implementation of approved changes as they occur; and
  8. Appropriate reporting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Monitor and Control inputs

A

PMPlan, Schedule forecasts, Cost Forecasts, Validated changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Monitor and Control inputs: PMPlan

A

Subsidiary plan list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Monitor and Control inputs: Schedule forecasts

A

derived from progress against the schedule baseline and computed time estimate to complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Earned value management

A

ETC, SV, SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Monitor and Control inputs: Schedule forecasts - ETC

A

Estimated to Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Monitor and Control inputs: Schedule forecasts - SV

A

Scheduled Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Monitor and Control inputs: Schedule forecasts - SPI

A

Scheduled Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If Earned Value Mgmt not used

A

Variances against planned finish date/forecasted finish date provided

17
Q

Monitor and Control inputs: Cost Forecasts

A

derived from progress against the cost baseline and computed estimates to complete (ETC).

18
Q

Monitor and Control inputs: Cost Forecasts - how is ETC expressed in CV/CPI

A

CV vs CPI
CV - cost variance
CPI - cost performance index

19
Q

Monitor and Control inputs: Cost Forecasts - CV

A

CV - Cost Variance

20
Q

Monitor and Control inputs: Cost Forecasts - CPI

A

CF - Cost Performance Index

21
Q

Monitor and Control inputs: Validated changes

A

Approved changes that result from the Perform Integrated Change Control process require validation to ensure that the change was appropriately implemented.

22
Q

Monitor and Control Inputs - EAC

A

Estimated at completion

23
Q

Monitor and Control inputs - BAC

A

Budget to completion

24
Q

Monitor and Control inputs - EAC vs BAC

A

To see if project is still within tolerance ranges or if change request is required

25
Q

Monitor and Control inputs - for projects not using earned value management, how to forecast cost?

A

Variances against planned vs actual expenditures and forecasted final costs

26
Q

Validated changes

A

Approved changes that result from the Perform Integrated Change Control process require validation to ensure that the change was appropriately implemented.

27
Q

work data transformed from what to what?

A

work performance data into work performance information (correlated and contextualized)

28
Q

Ex of work performance info

A

status of deliverables, implementation status for change requests, and forecasted estimates to complete.

29
Q

Enterprise Environmental Factors

A

Governmental or industry standards;
Organization work authorization systems;
Stakeholder risk tolerances;
Project management information system

30
Q

Org process assets

A
Organizational communication requirements;
Financial controls procedures ;
Issue and defect management procedures ;
Change control procedures;
Risk control procedures ;
Process measurement database ;
Lessons learned database.