CH 14 - Project Close Out, Evaluation & Support Flashcards
1
Q
- As Earl looks over a punch list, he learn of items that still need to be completed in order
to fulfill every condition of the contract. Generally, _______of these items are considered minor.
a. all
b. most
c. few
d. none
A
b. most
2
Q
2. Which of the following parties might be expected to file a lien on a property that is undergoing project work? a. the GC b. the subcontractor c. the facility manager d. the building owner
A
b. the subcontractor
3
Q
- Which project close out document shows modifications to the construction documents
and the actual location of building systems and equipment?
a. as-built drawings
b. punch list
c. Operating system documentation
d. Certificate of Substantial Completion
A
a. as-built drawings
4
Q
- It is critical that the building operating documentation be assembled immediately after
project completion while design engineers and installing mechanics are available because systems are:
a. not covered under warranty without notarized statements from designers and installers.
b. rarely installed exactly as they are designed.
c. best serviced by those who installed them.
d. inoperable until properly calibrated.
A
b. rarely installed exactly as they are designed.
5
Q
- POE (post-occupancy evaluation) questions should relate directly to the:
a. customer’s major tasks.
b. project objectives defined earlier.
c. personal feelings of the customer group.
d. results desired from the POE.
A
a. customer’s major tasks.
6
Q
- The type of POE (post-occupancy evaluation) that is best for small projects is:
a. diagnostic.
b. continuous.
c. investigative.
d. indicative.
A
b. continuous.
7
Q
- Frank may choose a(n) ______________approach for his mid-size project of 15,000 square feet.
a. diagnostic
b. continuous
c. investigative
d. indicative
A
c. investigative.
8
Q
- Which is true concerning the facilities management policy development process?
a. a good policy outlines a strict procedure to be followed for each project
b. a good policy is developed by group consensus
c. feedback on a policy should include appeals for future changes, but not exceptions for current projects
d. a policy is strongest when it represents personal convictions
A
b. a good policy is developed by group consensus
9
Q
- To make the process work most efficiently, the facilities policy committee at Andy’s organization should include:
a. only senior management.
b. only the facility manager and senior management.
c. representatives of all affected departments.
d. representatives of all departments whether they are affected or not.
A
c. representatives of all affected departments.
10
Q
- The ideal project for use in field testing a facilities management policy would be:
a. very small and short in duration.
B. An executive-level project
c. unique in comparison with other projects.
d. unlikely to generate protests or appeals.
A
d. unlikely to generate protests or appeals.
11
Q
- The Certificate of Beneficial Occupancy is obtained when:
a. at least half of the tenant space is filled.
b. the moving process is complete
c. inspectors have reviewed the building for code compliance.
d. all construction documents have been legally reviewed and approved.
A
c. inspectors have reviewed the building for code compliance.
12
Q
- Unlike an investigative POE, an indicative POE:
a. is casual.
b. is detailed.
c. is ideal for large projects.
d. requires a research strategy and plan.
A
a. is casual.