Q

What are three changes between CDM 2007 and 2015

A
  • CDM coordinator no longer a role. Principal designer introduced
  • Domestic jobs now need to comply with the regulations
  • notifiable 2007 30 days OR 500 person day; 2015 30 days with 20 people on site at any time OR 500 person days
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is a project notifiable?

A

either 30 day project with 20 people on site at any point
OR
500 person days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happens when a project is notifiable?

A

An F10 must be raised with the HSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What info is shown on an F10

A

As required under CDM 2015 schedule 1:
- Name, address, number, and email of the client, PD, and PC
- Planned start date and project duration
- The type of work
- the maximum number of people on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is required to be provided under Schedule 2 of CDM 2015?

A
  • Sanitary and wash facilities
  • Drinking water
  • Resting place with: area to boil water; space to prepare and eat food; maintained at an appropriate temperature
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the principal designer responsible for

A
  • Plan, manage, monitor H&S pre-contract
  • Review and maintain H&S file
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Principal Contractors role?

A
  • Plan, manage, monitor H&S on site
  • If the PD’s role ends before completion, the PC will review and maintain the H&S file
How well did you know this?
1
Not at all
2
3
4
5
Perfectly