Case study questions Flashcards
What was the acoustic requirement?
The Acoustic Performance Criteria specifies a noise rating derived from a number of readings pursuant to the Acoustic Testing Regime which rating does not exceed ‘NR’ R5 in each of the Auditorium (including the Control Room) and the Rehearsal Room separately. This is subject to testing.
What is box in a box construction?
Box-in-box is a construction technique that allows a space within a space to be insulated against unwanted noise and vibration.
The technique involves constructing a room within a building structure, so that the inner room is acoustically isolated from the outer.
What is the building frame made from?
It was a steel frame with composite slab. By joining the two materials together result in a highly efficient and lightweight design.Composite systems also offer benefits in terms of speed of construction
What are secant pile foundations?
A secant pile wall consists of primary piles which are cast first also called female or soft. The reinforced load bearing piles are drilled to intersect the female piles/columns and are called male or hard.
They provide:
Increased wall stiffness compared to sheet piles.
Can be installed in difficult ground (cobbles/boulders).
Less noisy construction
What other kind of foundations are there?
There are two types:
- Shallow foundation: Wall footing, combined footing, raft or mat foundation, cantilever foundation.
- Deep foundation: piles, pier or caisson
Can you explain what a two stage tender is ?
Two stage tendering is a method of procurement where the employer seeks to appoint a contractor at an initial stage of the project based on an outline scope of work. There is then a second stage when the employer seeks to appoint a contractor for the construction works under a building contract.
What other tender processes are there?
- Open tendering : allows anyone to submit a tender for the services required.
- Selective tendering: Selective tendering only allows suppliers to submit tenders by invitation
- Negotiated tendering: Negotiating with a single supplier may be appropriate for highly specialist contracts, or for extending the scope of an existing contract.
Framework tendering: Such arrangements allow the client to invite tenders from suppliers of goods and services to be carried out over a period of time on a call-off basis as and when required.
Tell me about the RIBA Stages
0 - Strategic Definition - Clients requirements confirmed
1 - Preparation and Briefing - Project brief approved by the client
2 - Concept Design - architectural concept approved by the client and aligned to project brief
3 - Spatial Coordination - architectural and engineering information spatially coordinated
4 - Technical Design - all design information required to manufacture and construct the project completed
5 - Manufacturing and Construction - Manufacturing, construction and commissioning completed
6 - Handover - Building handed over, aftercare initiated and building contract concluded
7 - In Use - Building used, operated and maintained efficiently
Explain the role of the CMT
They are appointed by the client following novation of the design team to check the building is being constructed as per the contract and raise and quality or design concerns.
What is novation
Novation is a process by which contractual rights and obligations are transferred from one party to another.
Benefits:
Continuity of design
What is magnamite are what are its uses?
It is a heavy natural aggregate which increases the density of the concrete by about 60%.
What is BREEAM?
Building Research Establishment Environmental Assessment Method. BREEAM is the world’s leading standard for design, assessment and certification of sustainable buildings. BREEAM addresses all aspects of environmental sustainability including management, health & wellbeing, energy, water, materials, waste, ecology and pollution. They range from unclassified to outstanding.
Why did you use JCT design and build?
Design and build can be advantageous in terms of time as it allows the overlap of design and construction reducing the overall project delivery time, contractor takes on most of the risk.
What are the other contract types?
Minor works contract,
Major works contract,
Management building contract
Construction Management contract
For this an alternative contract would have been the major works contract
What is your leadership style?
- Adaptable leader to the situation and individuals
What is your negotiation style
I am collaborative, I look for a win win, I establish what the other party is looking for and try to find a way to provide it whilst obtaining my own goal from the negotiation. Overall, I look to find a solution which doesn’t damage a relationship and both parties win. If I strongly disagree I can be more competitive (Win/Lose).
What are the RICS personal and professional standards?
Competence Ethical Behaviour Service Solvency CPD Information to RICS Cooperation
What is a PCSA
Precontract services agreement between the contract and client
What are the benefits of the PCSA?
- Improve the buildability and
- Cost-certainty of the design
- Creating a better integrated project team and reducing the likelihood of disputes.
What services were included in the PCSA?
- Review technical requirements of the project,
- Review risk register, pr
- Develop a programme,
- Lead the design,
- Advise on specialist consultants and sub contractors,
- Assist with VE,
- Assist with proposing alternative materials or methods of construction which would provide additional benefits,
- Review planning conditions,
- Recommend a procurement strategy for works packages,
What is concrete made of?
Cement, water and aggregate
What other kinds of procurement routes are there?
- Design and Build
- Traditional - Design first then build
- Construction Management: A construction manager is responsible for the construction. The Client is in contract with the subcontractors. The construction manager has no contractual link with the subcontractors
- Contract Manager route: Similar to the above apart from the contract manager has contractual links to the subcontractors as oppose to the Client.