Case Study - Key Issue 2 Flashcards
Was there a conflict between acting as Contract Administrator and Project Manager?
You always need to act in an impartial way. Role as a PM was clearly defind and if there were to be a conflict I would notify the parties and inform them I could no longer carry out both roles.
Why was a traditional procurement route chosen?
- Retain control over design.
- Nature of works not appealing to D&B contractors.
- Quality of finish harder to control, providing it meets employer’s requirements.
Why did you use a JCT Intermediate Building Contract with Contractors design portion?
- Sectional completion (Which is not available in minor works)
- Named events and matters as more complex work
- Named QS
- Some works designed by Contractor – M&E elements based on performance spec by Employer.
- Medium complexity – Over 4 sites.
What insurance proofs did you request from the Contractor?
Proffessional indemnity (For CDP element), Public liability,
Case study - What were your duties on this project?
Contract Admin – Administer the contract, issue instructions, certificates etc
At what stage did you advise the client to retain an additional 15% contingency?
Within the tender report. Note the additional 10% contingency defined.
Case study - When was the programme duration advised?
An indicative programme was included within the tender documents and the contractor returned one with their tender. The duration was included in the contract.
Case study - What type of provisional sum was included?
- Undefined provisional sum as the works could not be fully defined without access.
- This carried risk as the client bears the programme and cost risk.
- As it is not detailed, allowance in programming, planning, and pricing preliminaries is often not included by Contractor.
How was safe access agreed?
- Original details set out in Pre-Construction information (PCI) contained in tender.
- Contractor Construction Phase H&S Plan (CPP) agreed with Principal Designer.
- Proposals agreed on location of stairs away from public.
What guidance is there on the install of corrugated steel sheet roofs?
- BS 5427-1:1996 – the code of practice for profiled sheet cladding on buildings
- The Metal Cladding and Roofing Manufacturers Association
- National Federation of Roofing Contractors
What is cut edge corrosion?
- Rolls of steel sheets are applied with corrosion protection (e.g hot-dip zinc galvanising or zinc–aluminium alloy) and plastisol.
- Rolls are then cut into more manageable lengths, leaving the cut steel ends exposed to the elements.
- For an initial period, the exposed steel edges are protected by the zinc layer which corrodes “sacrificially” for the steel.
How can you prevent cut edge corrosion from the factory?
- In the long term, cut-edge corrosion is unavoidable.
- Premature edge corrosion can be reduced by specifying sheeting which is manufactured to minimise edge corrosion risk. For example, sheets with zinc–aluminium alloy have lower rates of sacrificial corrosion.
What are roof fasteners?
They fix the roofing sheets down to the roof structure below. They have a rubber washer to seal the fastener.
How do roof fasteners prevent water ingress?
They have a rubber seal / gasket that seals the hole to the roof.
Why does thermal movement occur to roofs
It occurs when heat is added to materials (Sun, temperature internally / externally), causing the material to expand. Consequently, removing the heat energy (cooling) causes the material to contract.
Cause of roof fastener failure? How was this confirmed, any tests to prove theory
Thermal movement caused the roof fasteners to back-out and water caused corrosion.
Why does water ingress cause roof deterioration?
Causes corrosion of the metal elements of the roof, as well as deterioration of timber elements.
What is an options appraisal?
- Presents the options for remediation as well as the benefits and drawbacks.
- Consider: Time / Cost / Quality
Did you consider safe access in your works specification?
Replacement ladders and fall restraint were considered, however, the costs were too high, so the client budgeted to carry out works themselves.
Why would a new roof bring about thermal improvements?
- Additional insulation would need to be installed.
- when more than 25% is being replaced
- Part L sets out U-Values requirements for new roofs in existing buildings (Table 4.1). Maximum U-value of 0.16 w/(M2K) to pitched roofs.
When would a thermal upgrade have been required to the roof?
a. More than 50% of the surface of the individual thermal element is renovated.
b. The work constitutes a major renovation. A major renovation is when more than 25% of the surface area of the external building envelope is renovated.
Case study - Were any other options available to the client other than those proposed?
Overcoating following cut edge corrosion treatment was considered but exceeded budget
How did you appoint the quantity surveyor?
Terms, fee and scope of services were agreed.
How was the budget cost prepared for the roof replacement?
Quantity surveyor was engaged and prepared a cost based on BCIS cost data and benchmarking.
What regulations would you have to consider with a roof replacement?
Roof regulations –
- Approved documents:
o Part A – Structure – Roofing Structure
o Part C – Site preparation and resistance to contaminants and moisture – Resistance to damage from Interstitial condensation, moisture from outside and surface condensation / mould growth
o Part H – Drainage and waste disposal – Rainwater disposal from the roof.
o Part K- Protection from falling, collision and impact – Protection from falling via Fall Arrest System
o Part L – Conservation of fuel and power – Improvements to U-value (Over 25% of roof being replaced)
o Regulation 7 – Materials and Workmanship
What was the roof overlay system explored to the roof?
Profiled metal roof overlaying existing roof
Why wasn’t a liquid overlay sytem considered? This wouldn’t have had a weight implication?
Client budget would have meant that additional monies would be required (Couldn’t be done in contingency).
This would have added significant time, with the works being difficult within the winter months.