Case Study - Key Issue 1 Flashcards

1
Q

What is a performance bond?

A

A financial guarantee provided by an insurer or bank as a means of insuring an employer against the risk of a contractor defaulting on any of its contractual obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What types of performance bond are there?

A

Conditional - Requires the Employer to evidence the Contractors non-performance and that they have suffered a loss.
On-demand - No evidence required to claim on performance bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Case study - Why was the contractor unable to obtain a performance bond?

A

Picture not 100% clear but some causes likely:
- Poor financial strength
- Difficulty in market to obtain performance bonds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Case study - What is a high financial gearing and what does this mean?

A

It is a ratio used to show how much a company depends on debt to fund its operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Case study - How much would a performance bond typically cost?

A

Variable but typically around 1%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Case study - How much would a performance bond typically cover?

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Case study - Did you consider taking out a project bank account whereby the contractor deposits a sum till completion?

A

This was considered, however, the Contractor did not like this route as it would effect their cash-flow and would cost them a lot upfront.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Case study - Did you consider a parent company gaurantee?

A

This was not applicable as their was no parent company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Case study - Did you carry out a credit check on the company as part of the tender process?

A

Relied on Clients credit check. Contractor was put forwards by them - Lesson learnt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Case study - Did you provide any legal advice on the options?

A

No as I am not a legal expert, however, I did liaise with the clients legal team to discuss the options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Case study - How did the enhanced retention work?

A

10% retention till 50% completed
7.5% retention till 80% completed
5% retention till sectional completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Case study - Would termination be possible within the JCT contract?

A

There are very specific requirements around termination which legal advice would need to be saught for. These are in Section 8 and include:
- Default by contractor
- Insolvency
- Corruption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Case study - Why do you think there is an issue obtaining performanc bonds in the market?

A
  • Market trends
  • Uncurtainty in the insurance market
  • Contractor liquidity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Case study - Did you draft the clause for inclusion in the contract?

A

No, this was drafted by the Client’s solicitor as this was outside of my area of expertise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Case study - If your JCT Contract was still in review and the retentions not set/agreed – could you not have awarded to the next most advantageous tenderer?

A

This was discussed with the Clients legal & procurement team. It was decided by them that it was too far progressed to change tenderer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Case study - What would you do in the future to ensure the tendering contractors were able to provide the performance bond included in their tender?

A

Ask to see a bonding capacity assessment/letter from a reputable surety company.

17
Q

Case study - Were there any other procurement options that were considered as part of these works

A

A framework could have been used like the CCS, however LDC like to use local contractors and the urgency to carry works out may not have been suitable for the number of returns.

18
Q

Case study - Why did you need a performance bond? Why is it a significant risk?

A

Risk as it was a public project so needed security to the tax payer.

19
Q

Case study - What regulations governs procurement in local authority projects?

A

Public contracts regulation 2015 (Will be superceded by the Procurement Act 2023, in Feb 25)

20
Q

Case study - What is the process for termination under the JCT contract suite?

A
  • CA issues notice to contractor
  • If specified default continues for 14 days the Employer can terminate
  • The employer has 21 days to terminate following expirey of the 14 days
21
Q

Case study - The project was procured traditionally, how did this impact the clients risk profile in construction?

A

The client would retain the design risk as they have prepared the designs for the tender.

22
Q

Case study - What is the commercial risk in terms of re-tendering that you considered? Appetite from the market?

A

Low apetite for the work. Could be a risk given the time of year works would have been carried out.

23
Q

Case study - What is the difference between a performance bond and retention?

A

Retention - provide the client with some security that the contractor/sub-contractor will return to correct any defects during the defects correction period, or defects liability period.

Performance Bond - Issued by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor.

24
Q

Case study - Wouldn’t an enhanced retention put them at an even higher financial gearing ratio and put them at even greater risk of insolvency?

A

The risk was presented to the cleint but was deemed to be sufficiently low. The Contractor was also comfortable with the proposal and that they could continue on the basis. Value of works sufficiently low that it should have a huge impact on the Contractor cashflow.