Case Study Flashcards

1
Q

As NRM 1, do we include a contingency for design development risks?

A

Yes, there is a allowance in NRM1 for design development risk, which is a percentage cost, so base cost estimate x by risk percentage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What were the perceived benefits of the 2-week PCSA period?

A

The client has been in discussions with the nomindated joinery subcontractor and architect and ID which we had not been party to and he had developed the design in his workshop. He was nervous about cost increases and due to this he wanted to utlise the time before start on site to obtain prices from the company and get ahead of the process of engaging them on the project as the joinery was on the Critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What design information was missing at contract award?

A

As it was a two stage tender design information was missing for the later packages, which is the normal however, when budgets were put together it was at RIBA stage 2 and not Stage 4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What needs to happen between contractor appointment and construction phase?

A

Design Checking Period
Cotractor produces Health and Safety information - CPHSP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How long should this period be?

A

Depends on the size of the project but normally 4 weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where is this set out?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did CDM apply to this project?

A

Yes the project was a notifiable project under CDM Regulations and this was documented in Recital 10 of the JCT contract.
F10 in place
Site set up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does the importance of Value Engineering relate to the client’s key drivers?

A

Value Engineering is the process of maximising value so as the client wanted to sale or rent the property this was key as VE can also mean reducing life cycle costs, reducing initial costs, reducing risk etc. However, in practice it appeared quality meant more to him than anythign else.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was your role in identifying the alternative construction solutions?

A

My role was to advise on the cost implications of the optioned proposed in a time manner to ensure the client made an informed decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Talk me through how you used your knowledge of construction technology to identify issues with Option B – Concrete Rib Deck?

A

Through my knowledge on construction technology I reviewed the proposed works and identified clashes on site, notably the steel being positioned where the existing box gutter was positioned. I also highlighed the movement of concrete through a property that has recently has new stairs installed. Chasing the party wall was also an issue as there was not once in place and finally the steel running from party wall to party wall would require a splice as it could not be craned in, this would incur further costs and design for steel connections which was not required previously.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Talk me through how you priced the variation Option C – Installation of shallow steel beams with internal timber joist work.

A

I priced the VO with rates from the CSA, ammended rates from the CSA, direct labour and material costs, plus a provisional sum for the bespoke drain which was yet to be designed. The roofing, leadwork, stainless steel gutter and scaffold were subcontractor costs. I also allowed a contingency for construction risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Talk me through the structure of your procurement schedule?

A
  1. Subcontractor Package
  2. Supplier Options
  3. Procurement Route
  4. CDP element
  5. Full Design Info
  6. Out to tender
  7. Tender Duration
  8. Tender Review
  9. Appoint Subbie
  10. Manufacture (survey, sign off + manufacture)
  11. Start on site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What were your reasons for engaging with the supply chain in respect of the Tier 1 joinery as Option A?

A

To prove value for money for the client, he was not an experienced client so therefore I found it important he understood the costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

As a QS, did you/the project team/client not have confidence that ‘I believed the costs provided to be a true representation….’?

A

I believe this is a tricky statement as it may not necessarily be a confidence thing but we had not worked with them before and a relationship needed to be built and I wanted to ensure they understood the cost increase and what elements were causing this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What benefit(s) did you consider engaging with the wider market for these works provided, to offset the additional time it took?

A

I know the clients main objective was quality so I wanted to make him aware this was a fair market value for what he has requested so he would feel more comfortable making a decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

From an ethical perspective, what issues were there in asking the supply chain to incur costs tendering for works that were unlikely to be awarded?

A
17
Q

Talk me through how you used the elemental cost plan to identify potential areas of Value Engineering?

A

Staircase - liquid metal handrail
Stone - Calacatta marble cut into tile format

18
Q

What advice did you give in respect to Key Issue 1?

A

My advice was for the client to proceed with Option 3, samples were presented and approved.

19
Q

Had you not undertaken Option A, would there have been a programme impact?

A
20
Q

Talk me through ‘the pitfalls of negotiated tendering’ as happened on this project?

A

Pre tender estimate was too far away from the price recieved, therefore the subcontractor could not have been appointed on the agreed date.

21
Q

What advice did you give with respect to Key Issue2?

A

Cost advice on a change and prolongation costs which were priced separately.