Case Study Flashcards

1
Q

What is a CAT B fit out?

A

a fully operational workplace that has been designed to a client’s unique specifications to make it their own

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does CAT B differ to CAT A?

A

CAT A is the basic finishing of an interior space (includes the installation of a building’s mechanical and electrical services), “blank canvas”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a deed of variation in a JCT contract?

A

DoV enables changes to a pre-existing contract without completely rewriting or terminating the original agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the differences between a Relevant Event and a Relevant Matter under a JCT building contract?

A

“Relevant Events” entitle the contractor to claim additional time and “Relevant Matters” entitle the contractor to claim additional costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an undefined provisional sum?

A

NRM2 states that this is a sum provided for work that is not completely
designed, and the information required for a
defined provisional sum cannot be provided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a defined provisional sum?

A

A sum provided for work that is not completely designed but has sufficient information provided - e.g. quantity/quantities indicating the scope, specific limitations, nature of the works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It appears the contract sum has more than doubled, what are the reasons for this?

A

As of May 2024:

Baseline contract sum was £15.6m.
The DoV added £14.6m.
Client change has added £3.3m.
EoT has added £2.2m.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you explain the three phases of the project

A

Based on the Client’s occupation needs - construction work can only take place on 2 floors out of 6 at a time.

Phase 1 - 53 weeks
Phase 2 - 40 weeks
Phase 3 - 29 weeks

(Aug 22 - Jan 25)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What were Extensions of Time for?

A

8 EOT’s

40 Relevant Events.

4x deferred site possession (project sequential phasing, knock-on effect)

2x discoverables

26x variations

8x prevention by client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Are you able to give some examples of the variations on this project given they are to a value of £2.6m* in December ‘23

A

170 CAI’s

CAI 45 - L2 & L4 Stage 4 design release (£250k)

CAI 46 - L5 & L6 Stage 4 design release (£190k)

CAI 16 - staircase services diversion (£80k)

CAI 97 - site discoverables (£50k)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does being the construction lead on Level 2 and 6 involve?

A

Manage all construction works
Maintain relationships
Prepare and issue reports
Lead design, progress and liasion meetings
Manage project programme
Ensure quality assurance as per PEP and quality plan
Coordinate site activities
Ensure H&S compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Explain how you maintain a relationship with the client in your role

A
  • Consistent communication & check ins
  • Encourage client participation (client is inexperienced in construction, exciting that they come on the journey)
  • Daily liaison meetings
  • Seeking feedback and staying open to ideas
  • Setting realistic goals
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How were the various stakeholders identified?

A

PRINCE2 defines stakeholders as any individual, group or organisation that can affect or be affected by a project/activity/risk.

W&C, JLL, G&T, Core 5, Perkins & Will, Chapmans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you give any examples of some of the risks that were identified on the risk register?

A

Works being stopped due to noise complaints

Consent to access / work (e.g. riser works, diversions)

Works being disrupted due to items discovered during surveys.

Goods Lift Dimensions & Capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When considering Option 1, how would you have assessed the ambient noise?

A

dB(A) level (A-weighted decibel)

It can be measured with a simple Sound Level Meter to measure the relative loudness of sounds as perceived by the human ear.

The dB(A) level is used to report ambient noise and noise intrusions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did you propose that construction tasks would be simulated

A

Listed standard tasks and equipment required and on what scale.

Arranged input/assessment from Client.

17
Q

Where would the noise monitors have been positioned in the building?

A

The monitors were positioned at each Core (3x Cores on a floor)

18
Q

When considering the process of noise complaints, did you consider what the complaint process would look like?

A

Yes - the agreed channel was that complaints would be centralised through the Client’s operations/facilities team who were accountable to the W&C staff. Issues could be raised via phone call, WhatsApp group, or email. All complaints had to be formalised though.

19
Q

Did the contract give any consideration to noisy works or nuisance?

A

Clause 3.15 Contract Administrator may issue instructions to postpone works.

No other reference

20
Q

What are the City of London noise pollution requirements you refer to?

A

City of London Code of Practice for Deconstruction & Construction Sites -

standard hours for noisy work:
- 8am-6pm Monday to Friday,
- 9am-2pm Saturday,
- no noisy works Sundays or public holidays
- ‘reduced impact hours’ 10am-12pm & 2pm-4pm Monday to Friday (put in place to give nearby commercial occupiers at least 4 hours without noisy working)

21
Q

For Option 2, could you have considered some of those ‘noisy works’ taking place at night when the property was not being used?

A

Yes it was considered, but ISG’s cost was conditional on works taking place in normal working hours (8am-6pm).

Working nights would have increased costs, and potentially detrimental to workforces mental health & wellbeing.

W&C typical working hours 10am-8pm.

22
Q

What are these wedge nuts that you refer to in Option 3?

A

Wedge nuts are used in rib deck construction in order to avoid drilling into the soffit directly. These slot in the rib, rotate until locked in position and then threaded rod can be inserted into the hole.

23
Q

Can you explain what you mean when you state that ISG had excluded any exemptions for noisy works?

A

During tender, ISG clarified that there is a defined provisional sum for out of hours working (staircase service diversions and slab break) but there were no further allowances for out of hours working within the tender. This was accepted by the Project Manager.

24
Q

Explain how the validations were undertaken

A

Validations schedule

Site and desktop inspections, test reports, measurements and photographs.

25
Q

How did you ensure separation between the works and occupied part of the floorplate?

A

Physical drywall hoardings to set out site boundary.

H&S signage

MEP service diversions to enable isolation within site demise but live supply in occupied areas (e.g. pipework loop, DB board electrical decommission).

26
Q

Can you provide more detail on intermittent access?

A

Any work area not defined as ISG’s under the HSE F10 required a permit to access from the Client - this required 48 hour notice. If access requests clashed with Client events or meetings, then access was rejected.

27
Q

How big were the areas that would be out of action to allow the validations?

A

Approximately 12,000 sq ft.

Included 15 meeting rooms, main reception, catering/kitchen facility and servery area, 3 conference rooms.

28
Q

How were cloud point surveys and 3D modelling useful for helping to identify a solution for noisy working issues?

A

Allowed the design of a 3D coordinated MEP and architectural model - materials could be prefabricated off site and delivered to reduce on-site material adaptions.

29
Q

At any point did you consider if there were some elements of noisy work that could have been undertaken off site or in a designated area outside of the building?

A

One reason a 3D model was coordinated/designed was so that materials could be pre-fabricated off-site. There was not an area outside of the building that could have been used.

30
Q

Did you not consider that you might be making life more difficult for yourself by trying to consider the noise disruption to such an extent?

A

Yes - but it was important that I offered a responsible and good quality of service to the Client and I ensured methods were in line with supply chain capability and expertise before sharing. I made no promises pre-tender and any suggestions were an added benefit.

31
Q

Did you not consider that construction works are noisy by nature and the Client would just have to accept it?

A

Yes - but I was responsible for offering a good quality of service and using my experience to solve problems associated with noise generation. One option was for the Client just to ‘accept it’ however, the Client was inexperienced in construction and I did not want to unsettle them unnecessarily.

32
Q

Can you explain why Option 2 (weekend access) and Option 3 (night access) are variations to the contract?

A

Under Clause 2.29.6 - the client was preventing access to areas required to safely complete fit-out works.

Weekend access would represent a change to the agreed method of working, and invite costs for non-productive overtime.

33
Q

Why could the validations not be undertaken without areas being out of action?

A

Validations access was ‘intrusive’.

The Client was not willing for my employer to be visibly carrying out any works, including visual checks.

34
Q

Why do you think the Client had reconsidered their acceptance of the original proposed plan?

A

The plan was agreed months before the task started as part of a programme workshop. When the time came to carry out the works, the Client was no longer willing to work to this plan.

35
Q

Can something be both a Relevant Event and a Relevant Matter?

A

Relevant matters should not be confused with relevant events.

Events - time
Matters - money

36
Q

Why was the night access programme quicker than the weekday access?

A

Larger areas could be surveyed at once because the works were deemed ‘less intrusive’.