Case Study Flashcards
What is a CAT B fit out?
a fully operational workplace that has been designed to a client’s unique specifications to make it their own
How does CAT B differ to CAT A?
CAT A is the basic finishing of an interior space (includes the installation of a building’s mechanical and electrical services), “blank canvas”.
What is a deed of variation in a JCT contract?
DoV enables changes to a pre-existing contract without completely rewriting or terminating the original agreement.
What are the differences between a Relevant Event and a Relevant Matter under a JCT building contract?
“Relevant Events” entitle the contractor to claim additional time and “Relevant Matters” entitle the contractor to claim additional costs.
What is an undefined provisional sum?
NRM2 states that this is a sum provided for work that is not completely
designed, and the information required for a
defined provisional sum cannot be provided.
What is a defined provisional sum?
A sum provided for work that is not completely designed but has sufficient information provided - e.g. quantity/quantities indicating the scope, specific limitations, nature of the works
It appears the contract sum has more than doubled, what are the reasons for this?
As of May 2024:
Baseline contract sum was £15.6m.
The DoV added £14.6m.
Client change has added £3.3m.
EoT has added £2.2m.
Can you explain the three phases of the project
Based on the Client’s occupation needs - construction work can only take place on 2 floors out of 6 at a time.
Phase 1 - 53 weeks
Phase 2 - 40 weeks
Phase 3 - 29 weeks
(Aug 22 - Jan 25)
What were Extensions of Time for?
8 EOT’s
40 Relevant Events.
4x deferred site possession (project sequential phasing, knock-on effect)
2x discoverables
26x variations
8x prevention by client
Are you able to give some examples of the variations on this project given they are to a value of £2.6m* in December ‘23
170 CAI’s
CAI 45 - L2 & L4 Stage 4 design release (£250k)
CAI 46 - L5 & L6 Stage 4 design release (£190k)
CAI 16 - staircase services diversion (£80k)
CAI 97 - site discoverables (£50k)
What does being the construction lead on Level 2 and 6 involve?
Manage all construction works
Maintain relationships
Prepare and issue reports
Lead design, progress and liasion meetings
Manage project programme
Ensure quality assurance as per PEP and quality plan
Coordinate site activities
Ensure H&S compliance
Explain how you maintain a relationship with the client in your role
- Consistent communication & check ins
- Encourage client participation (client is inexperienced in construction, exciting that they come on the journey)
- Daily liaison meetings
- Seeking feedback and staying open to ideas
- Setting realistic goals
How were the various stakeholders identified?
PRINCE2 defines stakeholders as any individual, group or organisation that can affect or be affected by a project/activity/risk.
W&C, JLL, G&T, Core 5, Perkins & Will, Chapmans
Can you give any examples of some of the risks that were identified on the risk register?
Works being stopped due to noise complaints
Consent to access / work (e.g. riser works, diversions)
Works being disrupted due to items discovered during surveys.
Goods Lift Dimensions & Capacity
When considering Option 1, how would you have assessed the ambient noise?
dB(A) level (A-weighted decibel)
It can be measured with a simple Sound Level Meter to measure the relative loudness of sounds as perceived by the human ear.
The dB(A) level is used to report ambient noise and noise intrusions.