Case Laws Flashcards
1
Q
What year was Hutton construction ltd v Wilson properties ltd case law?
A
2017
2
Q
What are the facts of the case?
A
- Alleged failures of payment applications and payless notice
- residential conversion works on a property
- dispute arose over hutton’s payment no.24 and a payless notice
- adjudication commenced – found favour of hutton based on the faileu of a vailed payless notice by Wilson
- Wilson didn’t pay
- Hutton commencing enforcement proceedings
- Wilson issued a draft part 8 application and claimed a wrong verdict
- Court concluded favour of Hutton entitled to the sum of £491,994.73 originally adjudicated
- Wilson failed to serve vailed pay less notices and provided no evidence contending part 8 application
3
Q
What year was City Inn Ltd v Shepherd Construction Ltd Case Law?
A
2003
4
Q
What are the facts of the case
A
- Delaying evet occurred
- Shepherd ltd failed to serve the correct notices, however architect gave 4 weeks of EOT
- Followed by an adjudication, awarded 5 weeks extra of EOT
- City Inn claimed to reverse the above decisions and claim liquidated damages.
- City Inn (client) was successful in court at first. As they didn’t provide any notices
- The courts said failure to comply with clause 13.8.1 was not a breach of contract
- Shepherd argued clause 13.8.5 was a penalty clause
- Also it stats they must provide notices when they formed the opinion that a delay would result. They didn’t form an opinion at the relevant time, they were not in breach of the clause.