Capital Project Appraisal Flashcards
Capital Project
Any project where there is initial expenditure and then, once the project comes into operation, a stream of revenues less running costs. (It does not have to involve the construction of a physical asset - for example a life insurer developing a new product)
Capital Project Appraisal
The process of deciding whether a particular project should or should not go ahead.
Purpose of Initial Appraisal
Determining whether the project is likely to satisfy the sponsoring organisation’s authorisation criteria for projects it is prepared to authorise.
Common initial appraisal criteria:
- Financial results expected
- Risk that these results may not be achieved.
- Achieving synergy or compatibility with other sponsor projects
- Satisfying “political constraints”, both within and without the sponsoring organisation
- Having sufficient upside potential
- Best utilization of investment funds or management resources
6 Stages of Detailed Appraisal
- Project definition and scope
- Evaluation of cashflows
- Risk Identification
- Analysis of Risks
- Risk mitigation
- Investment submission
Possible project definition and scope inclusions:
- Success criteria and how these will be measured
- Budget of the project
- Timescales involved including limits beyond which the project team’s responsibilities and powers will not extend.
- To whom (or which departments) the goals of the project apply (and who should not be affected)
- Responsibilities of those involved
- Exact responsibilities of the people involved in the project team.
- Connected issues for which the team is not responsible.
Evaluation of cashflows stage
There should be an evaluation of the most likely cashflows for capital expenditure, running costs, revenues and termination costs.
The cashflows should allow for any consequential effects on the sponsor’s other activities or costs.
4 Important calculations when evaluating cashflow (Discounted cashflow approach)
- Net present value (NPV - will be regarded as satisfactory if it is positive)
- Internal rate of return (IRR - will be regarded as satisfactory if it exceeds a predetermined “hurdle rate” )
- Payback period
- Discounted payback period
Net Present Value Calculation
Models all cash flows of a project until termination and discounts these back to the present day using the cost of capital as discount rate.
If the result is positive then the project will improve shareholder returns.
Internal Rate of Return (IRR) Calculation
Similar to NPV, but rather than discounting the cost of capital, a solution is found for the interest rate that gives the project a zero NPV.
This method has the benefit of highlighting the return achieved by the project.
Practical problems with the IRR approach
- Nonsense results can be obtained if the initial capital is small giving very high positive (or negative) solutions, two solutions or none at all.
- The average NPV of a range scenarios can be found simply by summing the value multiplied by the probability of the scenario. The same is not true for IRR.
Pay Back period
Time it takes for the accumulated cashflow to become neutral.
(The project with the fastest payback period will be preferred, the method can also be used to identify the project that generates the most funds over a specific time period)
Sensitivity analysis
Analyses how the value of the project changes with differing future conditions. We take each key assumption in turn and assess the effect on the NPV of the most optimistic and pessimistic results occurring. In this way, we can identify which are the variables which have the greatest effect on the outcome of the project & determining where more information is needed.
Sensitivity analysis calculation
We take each key assumption in turn and assess the effect on the NPV of the most optimistic and pessimistic results occurring. In this way, we can identify which are the variables which have the greatest effect on the outcome of the project & determining where more information is needed
Scenario testing calculation
Consider plausible combinations of input values and see what effect these have on the project.