Capital Project Appraisal Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Capital Project

A

Any project where there is initial expenditure and then, once the project comes into operation, a stream of revenues less running costs. (It does not have to involve the construction of a physical asset - for example a life insurer developing a new product)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Capital Project Appraisal

A

The process of deciding whether a particular project should or should not go ahead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Purpose of Initial Appraisal

A

Determining whether the project is likely to satisfy the sponsoring organisation’s authorisation criteria for projects it is prepared to authorise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Common initial appraisal criteria:

A
  • Financial results expected
  • Risk that these results may not be achieved.
  • Achieving synergy or compatibility with other sponsor projects
  • Satisfying “political constraints”, both within and without the sponsoring organisation
  • Having sufficient upside potential
  • Best utilization of investment funds or management resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

6 Stages of Detailed Appraisal

A
  • Project definition and scope
  • Evaluation of cashflows
  • Risk Identification
  • Analysis of Risks
  • Risk mitigation
  • Investment submission
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Possible project definition and scope inclusions:

A
  • Success criteria and how these will be measured
  • Budget of the project
  • Timescales involved including limits beyond which the project team’s responsibilities and powers will not extend.
  • To whom (or which departments) the goals of the project apply (and who should not be affected)
  • Responsibilities of those involved
  • Exact responsibilities of the people involved in the project team.
  • Connected issues for which the team is not responsible.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Evaluation of cashflows stage

A

There should be an evaluation of the most likely cashflows for capital expenditure, running costs, revenues and termination costs.
The cashflows should allow for any consequential effects on the sponsor’s other activities or costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4 Important calculations when evaluating cashflow (Discounted cashflow approach)

A
  • Net present value (NPV - will be regarded as satisfactory if it is positive)
  • Internal rate of return (IRR - will be regarded as satisfactory if it exceeds a predetermined “hurdle rate” )
  • Payback period
  • Discounted payback period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Net Present Value Calculation

A

Models all cash flows of a project until termination and discounts these back to the present day using the cost of capital as discount rate.

If the result is positive then the project will improve shareholder returns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Internal Rate of Return (IRR) Calculation

A

Similar to NPV, but rather than discounting the cost of capital, a solution is found for the interest rate that gives the project a zero NPV.
This method has the benefit of highlighting the return achieved by the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Practical problems with the IRR approach

A
  • Nonsense results can be obtained if the initial capital is small giving very high positive (or negative) solutions, two solutions or none at all.
  • The average NPV of a range scenarios can be found simply by summing the value multiplied by the probability of the scenario. The same is not true for IRR.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Pay Back period

A

Time it takes for the accumulated cashflow to become neutral.
(The project with the fastest payback period will be preferred, the method can also be used to identify the project that generates the most funds over a specific time period)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sensitivity analysis

A

Analyses how the value of the project changes with differing future conditions. We take each key assumption in turn and assess the effect on the NPV of the most optimistic and pessimistic results occurring. In this way, we can identify which are the variables which have the greatest effect on the outcome of the project & determining where more information is needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sensitivity analysis calculation

A

We take each key assumption in turn and assess the effect on the NPV of the most optimistic and pessimistic results occurring. In this way, we can identify which are the variables which have the greatest effect on the outcome of the project & determining where more information is needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Scenario testing calculation

A

Consider plausible combinations of input values and see what effect these have on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

(Monte Carlo) simulation

A

Analysis to consider all possible combinations.

The entire distribution of thousands of possible project outcomes are considered.

17
Q

4 Risk identification stage steps

A
  • Make a high-level preliminary risk analysis.
  • Hold a brainstorming session of project experts and senior internal and external people who are used to thinking strategically about the long term.
  • Carry out a desktop analysis to supplement the results from the brainstorming session, by identifying further risks and mitigation options, researching similar projects undertaken by the sponsor or others in the past.
  • Set out all identified risks in a risk register, with cross-references to other risks where there is independency.
18
Q

The purpose of high level preliminary risk analysis

A

To confirm that the project does not obviously have such a high-risk profile and that it is not worth analysing further.

19
Q

4 Aims of the brainstorm session with project experts:

A
  • Identify project risks
  • Discuss risks and their interdependency
  • Place a broad initial evaluation on each risk.
  • Generate initial mitigation options
20
Q

2 Considerations in evaluating a risk:

A
  • Frequency of occurrence

- Probable consequences

21
Q

Analysis of specific risks will confirm:

A
  • Frequency of occurrence
  • Consequences if the risk occurs
  • Correlations between risks
  • Controllability of the risks
22
Q

Process of risk analysis

A
  • Concentrate on independent risks. Regard dependent risks as consequences of them.
  • Express financial consequences in present-day money values
  • Prioritize risks for further analysis. Discard risks with lower expected NPV’s, with the intention of allowing for them in a general contingency allowance later.
23
Q

6 Methods of risk mitigation

A
  • Risk avoidance
  • Risk reduction i,e. either reducing the probability of the occurrence or the consequences or both
  • Reducing Uncertainty
  • Transferring risk
  • Insuring risk
  • Sharing risk with another party
24
Q

What is to be assessed in mitigation option evaluation? 5 points

A
  • Likely effect on frequency, consequence and expected value,
  • Feasibility and cost of implementing the option
  • Any “secondary risks” resulting from the option (side effects)
  • Further mitigating actions to respond to secondary risks
  • Overall impact of each option on the distribution of NPVs
25
Q

Contents of the investment submission

A
  • Assumes that the best possible combination of mitigation options will be implemented

Contains:

  • Expected NPV
  • Probability distribution of NPVs
  • Identification & analysis of residual risks
  • Proposed finance method
  • Analysis of the likely effect on investors (after taking account of expected price inflation, borrowing, tax etc.)
26
Q

The essential aim of the investment submission

A

To discuss how the project relates to the sponsor’s criteria for judging whether or not to proceed with a project.

27
Q

Two distinct components of project-associated risk

A

Systemic risk

Specific risk

28
Q

Systemic risk

A

That part of the variability of return on a project which cannot be eliminated by investing in the same type of project many times over, or by diversification, because investing in a number of projects cannot reduce this part of the variability to zero.

29
Q

Specific risk (or probabilistic risk)

A

Element of risk that can be eliminated either by repeated investment in the same project, or by diversification over a number of different risk.

30
Q

Weighted average cost of capital =

A

(Market value of debt)/(Market value of debt & equity) x Debtholders’ required return x (1 - t)
+
(Market value of equity)/(Market value of debt & equity) x Shareholders’ required return

31
Q

The cost of debt capital is taken as…

A

the cost in real terms of new borrowing by the company.

32
Q

The cost of debt calculation

A

Calculated by taking an appropriate margin over the current expected total real return on index-linked bonds, and multiplying by (1 - t)

t = assumed rate of corporation tax.

33
Q

The cost of equity

A

The current expected total real return on index-linked bonds plus a suitable margin to allow for the additional return that equity investors seek to compensate them for the risks they run.

34
Q

5 Steps to produce a probability tree

A
  1. Map the possible choices, beginning from the initial project decision and branching out to represent all the possible subsequent options.
  2. Assign estimated cashflows associated with each future possible choice
  3. Estimate the probabilities associated with each future cashflow
  4. Use standard expected value calculations, incorporating both the time value of money and the probabilities to assess the optimal choices in each future time period, based on the knowledge of the intervening events.
  5. Work backwards from the latest decision point to the present day in order to establish the best route to follow at the outset.
35
Q

Three project appraisal considerations

A

Financial
Political
Strategic