Calculations Flashcards

1
Q

Planned Value (PV)

A

The value of the work you plan on completing during a specific period of time in the project schedule. Or it is the authorized budget assigned to scheduled work.
The formula is Planned Percentage Complete * Budget at Completion(BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value (EV)

A

The value of work that’s actually been performed or completed. Or it’s a measure of work performed expressed in terms of the budget authorized for work.
The formula is the Actual Percentage Complete * Budget at Completion(BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Cost (AC)

A

The actual money spent on the project at a given point in time. Or it is the realized cost incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion (BAC)

A

The total budget for the project or the sum of all budgets established for the work to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Variance (SV)

A

The difference between the work you planned to do and what you actually did at a specific point in time. The formula is Earned Value (EV) - Planned Value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Variance (CV)

A

The difference between the costs you planned to spend and what you actually spent at a specific point in time. The formula is Earned Value (EV) - Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Performance Index (SPI)

A

Measures the efficiency of the work put into a project at a specific point in time. The formula is the ration of Earned Value (EV) / Planned Value (PV) A number less than 1 is a sign the project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A

Measures the efficiency of the money spent on a project at a specific point in time. The formula is the ratio of Earned Value(EV) / Actual Cost (AC) A number less than 1 is a sign the project is over cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC)

A

Based on project performance, the cost at the end of the project may be more or less than what was budgeted (BAC). The formula is the Budget at Completion / Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate to Completion (ETC)

A

Takes into consideration what you’ve spent to date then evaluates team performance, and then provides a cost of how much the remaining work will cost to complete. the formula is the Estimate at Completion (EAC) - Actual Costs (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at Completion (VAC)

A

Calculates the difference between the Budget at Completion (BAC) and the Estimate at Completion (EAC) The formula is the Budget at Completion - Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index (TCPI)

A

Measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specific management goal. The formula is the (Budget at Completion (BAC) - Earned Value (EV)) / (Budget at Completion (BAC) - Actual Costs (AC). Numbers above 1 are bad.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Number of Communication Channels for a Project

A

There is a simple formula for figuring out the number of communication channels: n(n-1)/2, where n is the
number of stakeholders.
For example, a project with 5 stakeholders would look like this: 5(5-1)/2=5(4)/2= 20/2=10 communication
channels.
Understanding how many communication channels there are helps the project manager determine how
many stakeholders to communicate with, how to communicate with them, how much detail to use, how
often to communicate, and who will send the communication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Beta Distribution

A

Uses PERT with but weighs the realistic estimate more heavily. P+(4)R+ O / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Project Budget

A

Management Reserve + Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost Baseline

A

Sum of all Control Accounts

17
Q

Control Accounts

A

Contingency Reserve + Work Package Cost Estimates

18
Q

Work Package Cost Estimates

A

Activity Contingency Reserve + Activity Cost Estimates

19
Q

Burn Rate

A

The rate at which the project budget is being spent. The formula is 1/CPI

20
Q

Order of Magnitude Estimate

A

-25% to +75%

21
Q

Preliminary Estimate

A

-15% to +50%

22
Q

Budget Estimate

A

-10% to +25%

23
Q

Definitive Estimate

A

-5% to +10%

24
Q

Mean

A

Average of the numbers when summed up and divided by the number of values.

25
Q

Median

A

Middle value of a sorted array of numbers.

26
Q

Mode

A

The number that is repeated the most.