C. Managing projects Flashcards
what are the key attributes of a project?
- unique undertaking
- specific objective
- defined beginning and end
- project has allocated resources
- stakeholders
- some degree of uncertainty
- integrated into day-to-day once completed
what is the definition of a project?
a human activity that achieves a clear objective against a time scale
- team put together for this
- disbanded after completion
what is project management?
managing of the work of a team or teams to achieve specific goals and objectives
-project manager will report to project sponsor
‘the integration of all aspects of a project, ensuring that the proper knowledge and resources are available when and where needed, and above all to ensure that the expected outcome is produced in a timely, cost-effective manner’
what are the primary constraints of a project i.e. the project triangle?
time cost and quality
- might be conflicting nature
- time and cost and quality positively correlated
what are some other constraints on a project?
- legal
- technological
- political
- environmental
- ethical
what happens through the identification of a need stage of the project life cycle?
- a feasibility study is done to check benefits, alternatives and lifetime costs
- at the end of phase 1, company decides whether to proceed
- if they continue, a PID is raised
what is a PID?
a project initiation document
- includes vision and a business case for the project
- guide to decision-making throughout the project
- encourages motivation and congruent goals in the project team
what is the development of a proposed solution stage?
- all proposals submitted and evaluations
- most appropriate solution to satisfy the need will be selected
what is the implementation stage of a project?
- actual performance of project
- detailed planning
- implement plan
- solution divided into separate deliverables to achieve milestones
- achievements may be linked to stage payments
- project objectives monitored
- action any deviations
what is the completion stage of a project?
- confirm deliverables met and accepted
- payments finished
- performance evaluated and appraised
- obtain customer feedback
- check whether any subsequent actions are needed to ensure achievement of the anticipated benefits
how is the PMI’s 5 step project management process different to the project lifecycle graph?
more emphasis on the ‘planning’ and ‘controlling\ activities
what happens in the initiating stage of the project management process?
- initiated when a need or objective is defined
- might have to select from competing projects
- pick most worthwhile
how do companies decide the most worthwhile project to undertake?
feasibility
risk and uncertainty of project
who conducts feasibility assessment?
- sometimes project manager is involved in feasibility study
- they need to understand feasibility assessment
what are the different types of feasibility?
technical
social (operational)
ecological (environmental)
economic (financial)
what is social (operational) feasibility?
assess operational and social factors of implementation
- people required
- skills required
what is ecological(environmental) feasibilty?
-may be driven by the understanding that customers would prefer to purchase alternative products or services due to eco factors
what is the CBA performed during economic feasibilty?
- financial costs:NPV, IRR, payback
- look at multiple measures
benefits:
- tangible benefits
- intangible benefits, which would be excluded usually
costs:
- capital costs
- revenue costs:repairs, consumables
- finance costs:interest
what are the primary reasons for having a PID?
- for AUTHORISATION by project steer co or board
- act as BASE DOCUMENT against which progress and changes can be assessed
what does a PID include to show stakeholders are in general agreement?
- defines the project and its scope
- justifies the project
- secured funding for the project, if necessary
- defined the roles and responsibilities of project participants
- gives people the information they need to be productive and effective right from the start
what is the contents of a PID?
- purpose statement:why undertaken
- scope statement:major activities outlined
- deliverables
- cost and time estimates
- objectives:clear mission, CSFs and milestones
- stakeholders
- chain of command:project org structure
what is the need for planning stage in a project?
- communicate what has to be done, when and by whom
- encourage forward thinking
- provide the measures of success for the project
- make clear the commitment of time, resources (people and equipment) and money required for the project
- determine if targets are achievable
- identify the activities the resources need to undertake
what are the separate detailed plans drawn up during a project?
- time
- quality
- resources
- contingency for risks
- cost
- communication
- deliverables
what are the responsibilities of a project manager?
- primarily:define the project objective
- then communicate this objective
- make it clear what constitutes a successful project outcome
how is quality of a project measured?
customer satisfaction
-e.g. bugs in computer system, response times
other than project time, cost and quality, what is an important constraint of projects?
scope/functionality
- work that must be carried out to satisfy project’s objective
- manage variations of scope and agree on them
how long is the executing stage of a project?
can be weeks, months or years long
change is an inevitable part of any project, how can it be controlled?
- have a change management process
- can occur at any stage
- use PID and detailed project plans as baselines against which change is measured
- ensure changed are communicated before they are implemented
what are the problems if change is not managed?
- working on old plans meaning time is wasted and no longer relevant
- project is unlikely to deliver the set objectives if change is not well managed
- end users unhappy if not aware of issues
- project may cost more or continue for longer
- cause confusion and conflict for the project stakeholders
what should a change management process include?
- methods for prioritising changes requested:changes that must be done and would be nice to have
- authorisation for changes
- agreement of a change budget
- recording of changes:who will?
- communication of changes
what is configuration management?
tracking and controlling all aspects of the projects and all documentation and deliverables from the project
what is included in configuration management?
- version control for documentation
- ownership and responsibility for documentation
- authorisation and tracking procedures for any changes required to documentation
- monitoring and control procedure to ensure only authorised documents and records are held
- access control over projects records
what is the most important aspect of project control?
ensuring that monitoring progress is carried out and reported on a regular basis
what must a project manager do if they spot deviation?
- report the deviation
- obtain authorisation if necessary
- take corrective action to get the project back on track
-set up regular reporting period depending on complexity
what are the main purposes of a control system?
- prevention of deviations
- correction of deviations
- prevention of any future deviations by revising plans, target, measures
- implementation of recommendations from monitoring, reviewing and evaluating the project
what is performance management?
required throughout project in order to assess the progress of each aspect of the project
what are the measurements to assess a project’s performance?
- scope performance measures
- functional quality measures
- technical quality performance measures
- client satisfaction measures
what do conformance management systems focus on?
- inspection
- quality control
- quality assurance
what are the 2 most important elements used in the control of projects and reports and meetings?
reports and meetings
what is a project reports?
enhance and facilitate the communication of control and progress throughout the life of the project, the main reports are produced:
- exception reports
- progress reports
what is a exception report? what is a progress report?
exception: only report exception
progress: both formal and regular, update on project
what is the difference between team meetings and project progress review meetings?
team:regular, formal/informal, with project team
project progress review:regular, formal, involve project manager, team members and customer or steering com
what are a number of activities that must be undertaken in the closing stage of the project?
- project is delivered to users
- end of project meeting
- formal sign off of project
- project review meetings
- final report issues
- project team disbanded
what takes place in the internal end of project review meeting?
with team:
- an opportunity to review the planning, management, reporting and control
- an opportunity to discuss the success and failures of the project process
- to establish what can be learned in future for the benefit of other projects
- an opportunity for the project manager to discuss with individual team members their role in the project and the means by which they could improve their own performance on future projects
what takes place in the external end of project review meeting?
with customer:
- a crucial aspect of project closure
- an important part of establishing whether the project has satisfied the customer’s requirements
- to obtain feedback to help improve future projects
- when customers can voice any concerns regarding how the project was carried out
what are the constraints of the final report?
- brief overview of project
- customer original requirements and original project deliverables
- list of deliverables which the customer received
- actual achievements re costs, schedules and scope
- degree to which the original objective was achieved
- future considerations
what documents should be referenced before the final report?
- feasibility study and report
- PID
- project planning reports
- milestones and gates
what is the purpose of the closing stage of the process?
- ensure completion and conforming
- formal comparison to PID and project outcomes
- evaluate against agreed levels
- costs completed
- time comparison
- effectiveness of the management process
- complete project termination activities
- provide continuous improvement and feedback
- learn from experience
what is the Post Completion Audit (PCA)?
- carried out a few months after the project is completed
- designed to REVIEW the success of the project as a whole as well as to receive the user’s feedback on it
- establish whether project brought benefits
- improve knowledge for future projects
what are the key areas of the post completion audit?
- technical performance review
- quality level achieved
- benefits achieved
- cost/budget performance
- schedule performance
- effectiveness of project planning and control
- team relationships
- problem identification process
- customer relationships
- communication
- risk evaluation and assessment
- outstanding issues
- recommendations for future management of projects