Brehm2 Flashcards
Deterministic Project Analysis
ERM uses deterministic inputs to estimate internal rate of return by line; management makes decisions based off on these figures
Risk Analysis (DFA)
forecasted distributions of inputs (not single point estimate)
monte carlo simulation then calculates distribution of present value of cashflows and IRR
risk judgement is intuitively applied by decision makers
why is Risk Analysis (DFA) better than deterministic project analysis?
directly incorporates uncertainty of critical variables in model
Economic value added
EVA=NPV return-cost of capital
if EVA is positive, project adds value to firm and company should move forward
cost of capital (RORAC)
RORAC = return on risk adjusted capital
RORAC = risk-adjusted capital*hurdle rate
risk-adjusted return = return measure/risk measure
hurdle rate
hurdle rate is similar in concept to required return on capital from Goldfarb
can use CAPM to calc ie k
certainty equivalent approach and why it could be beneficial
similar to risk analysis
quantifies risk judgement with corporate risk preference or utility function for consistency
corporate risk policy can help insurer make more consistent and objective management decisions
corporate risk preference isn’t appropriate for diversified investors because investors only care about systematic risk since form specific risk can be diversified portfolio
economic capital
economic capital is measured with V@R at remote probability level similar to default probabilities of bonds ie 1-in-3000
VaR is not calculated by summing up contributions of ind business units; instead usually calculated for all risks combined and then allocated down to individual units
- choice of probability level used is fairly artificial
- target level is often selected so economic capital is slightly less than actual capital being held
economic capital advantages
provides unifying measure for all risks across an organization
more meaningful for management than risk-based capital or capital adequacy ratios
forces firm to quantify risks it faces and combine them into probability dist
provides framework for setting acceptable risk levels for an organization as whole and for individual business units
modeling challenges for economic capital
ERMs aren’t reliable at such remote probabilities because of approximations, assumptions, and lack of data in tail
ie probability level of 1-in-3000 is VWR-99.97 which is impractical to model
approach to set capital requirements that overcomes modeling challenges with economic capital
company can use impairment, rather than insolvency as reference point for probability level
ex: if company wants capital level to be adequate so that average 1-in-100 year result destroys no more than 25% of capital, then would set minimum capital requirement at 4x TVaR-99
VaRp%
=percentile of distribution @ probability p%
-it is single point so does not provide much info on distribution
TVaRp%
=E[L|L>VaRp%] = tail value at risk
-linear in tail so does not reflect that risk that is 2x large is more than 2x as bad
XTVaRp%
=TVaRp%-mean = excess tail value at risk
expected policyholder deficit
EPD=(1-p%)(TVaR-VaR)
-unconditional expected value of defaulted losses if there is a default