Brain Dump Flashcards

1
Q

Define PV

A

(planned value) Percent complete of where the project should be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define EV

A

(earned value) percent complete x budget at completion

What is the value of the work you have completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CV= EV-AC (describe/define equation)

A

Cost Variance = earned value - actual cost

This tells you if you are over or under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SV= EV-PV (describe/define equation)

A

Schedule Variance = earned value - actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does EV tell you?

A

Earned value tells you the value of the work that you have already completed. (if your actual cost is over your earned value you are over budget, if your actual cost is below your earned value you are under budget, if your actual cost equals your earned value you are on budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What formula tells you if you are over or under budget? How do you know?

A

Cost Variance (CV=EV-AC).

If your CV is a positive number you are under budget (GOOD)
If your CV is a negative number you are over budget (BAD)
If your CV is zero you are meeting your budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What formula tells you if you are on schedule? How do you know?

A

Schedule Variance (SV= EV-PV).

If your SV is a positive number you are ahead of schedule (GOOD)
If your SV is a negative number you are behind schedule (BAD)
If your SV is zero you are meeting your schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI=EV/AC (describe/define equation)

A

Cost Performance Index= Earned Value / Actual Cost

*** tells you over or under budget in percentage. Is good for portfolio management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What formula tells you if you are over or under budget when you have a lot of projects under a portfolio?

A

Cost performance index (CPI=EV/AC)

If your CPI is a greater than one you are under budget (GOOD)
If your CPI is a less than one you are over budget (BAD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

SPI=EV/PV (describe/define equation)

A

Schedule performance index= earned value / planned value

*** tells you ahead or behind schedule in percentage. Is good for portfolio management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What formula tells you if you are ahead or behind schedule when you have a lot of projects under a portfolio?

A

Schedule Performance Index (SPI= EV/PV).

If your SPI is a greater than one you are ahead of schedule (GOOD)
If your SPI is a less than one you are behind schedule (BAD)
If your SV is zero you are meeting your schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EAC=BAC/CPI (describe/define equation)

*When do you use this equation?

A

Estimate at completion= budget at completion/ cost performance index

  • You are assuming the future work on the project will move at the same rate as the cost performance index
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

ETC=EAC-AC (describe/define equation)

A

Estimate to complete= Estimate at completion- actual cost

*Tells us how much money we still have left to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

TCPI= (BAC-EV)/(BAC-AC) (describe/define equation)

A

To-complete performance index = (budget at completion - earned value)/ (budget at completion - actual cost)

*performance index of how the project is going

If TCPI is greater than one this is bad
If TCPI is less than one this is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

TCPI= (BAC-EV)/(EAC-AC) (describe/define equation)

A

To complete performance index= (budget at completion - earned value)/(estimate at completion - actual cost)

*We use if the BAC is no longer relevant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the two equations for TCPI?

A
TCPI= (BAC-EV)/(BAC-AC)
TCPI= (BAC-EV)/(EAC-AC)
17
Q

VAC=BAC-EAC (describe/define equation)

A

variance at completion = budget at completion - estimate at completion

18
Q

What is the way to memorize the PMP equations (mnemonic device)?

A

Please (planned value)
Eat (earned value)
Carol’s (cost variance)
Sweet (schedule variance)
Cake & (cost performance index)
S (schedule performance index)
E (estimate at completion)
E (estimate to complete)
The (to-complete performance index - BAC)
Terrific (to-complete performance index - EAC)
Violinist (variance at completion)

19
Q

What is the way to memorize the Process groups (mnemonic device)?

A
In                (initiating)
Physical      (planning)
Education   (executing)
Mary Cries   (monitoring & controling)
Constantly   (closing)
20
Q

What is the way to memorize the Knowledge Areas (mnemonic device)?

A
I            (Integration)
Saw      (scope)
Six         (schedule)
Cars      (cost)
Quickly  (quality)
Rip           (resources)
Carols     (communication)
Rear       (risk)
Passenger   (procurement)
Seat           (stakeholder)
21
Q

What is the number of processes for the process groups (mnemonic device)

A

2-24-10-12-1

2    In                (initiating)
24 Physical      (planning)
10  Education   (executing)
12  Mary Cries   (monitoring & controling)
1    Constantly   (closing)
22
Q

What is the number of processes for the knowledge areas (mnemonic device)

A
766-436-3734
7      I            (Integration)
6      Saw      (scope)
6      Six         (schedule)
4      Cars      (cost)
3      Quickly  (quality)
6      Rip           (resources)
3      Carols     (communication)
7       Rear       (risk)
3      Passenger   (procurement)
4      Seat           (stakeholder)