Q

steps of using a control chart?

A
  • get preliminary data
  • find central line and control limits
  • check for values out of control
  • remove subgroups with assignable causes of deviation (not part of natural variation)
  • repeat
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what happens when Xdoublebar and Rbar are representative of the process?

A

they become Xbar0 and R0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How to recalculate the central lines?

A

sum of averages minus sum of discarded averages. Then divide by the new number of subgroups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which subgroups to remove?

A

either:

  1. subgroups with either Xbar and R is out of control with assignable cause.
  2. subgroups with both Xbar and R is out of control with assignable cause.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

how to work out the standard deviation from the average range?

A
standard deviation (sigma0) = R0/d2
(from sheet, with n=values in each subgroup)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what happens to the control limits with each revision?

A

they become narrower, range limits lower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly