Black Spectacles - Exam Questions Flashcards
What are some examples of project closeout documents?
- Completed punch list
- Final change order
- Guarantees and warranties
- Final waiver of liens
When will a building require an electrical power commissioning plan?
When it has a Critical Operations Power System (COPS) aka. some function of the building that will need to continue operating during an emergency.
What is a slump test?
Tests concrete for consistency/workability. Fresh concrete is placed in a cone, then the cone is removed allowing the fresh concrete to “slump”. The amount of slump is then measured. A collapsed slump means the mixture is too wet.
What is In-situ load testing?
A test that simulates the anticipated loads on a structure.
When should a mold expert be consulted?
When the affected area is more than 10sf
What can a full-size mock-up help envision?
- Safety and welfare of occupants by checking the structural integrity
- Pinpoint water penetration weakness
- To validate the design.
What process evaluates temperature and controls to ensue that they are working according to the design specifications?
Testing, Adjusting, and Balancing (TAB)
What is a UL rating?
Verification that the material was tested and deemed acceptable for safe use.
What is IIC?
Impact Isolation Class. This measures an assembly’s ability to absorb noise caused by impact to a floor/ceiling assembly. To reduce impact noise, the IIC rating of an assembly should be INCREASED!
What are Walers?
Horizontal elements used to support excavation sheeting.
What are Rakers?
Angled wood supports which extend from the ground of an excavation site up to the walls.
What is Crosslot bracing?
Exactly what it sounds like. Horizontal bracing which extends across the ground of the site from one wall to the other.
What are some responsiblities of a Low Voltage consultant?
Communications, security, audio, and video systems.
Where should the architect look when trying to find out how to process the field report?
Division 01 of the specifications
Who is responsible for code compliance?
The Architect
What is in the Commissioning Plan?
This is a document used to outline the scope and define the responsibilities of the commissioning process as well as the activities, schedules, and documentation required.
What is the Operations and maintenance manual (O&M)
The operations and maintenance manual (O&M) is a manual that contains all the information required for the operation, maintenance, decommissioning, and demolition of the building.
What is the Basis of Design?
The basis of design (BOD) is a term used to describe the drawings and specifications which are developed according to the owner’s project requirements (OPR). The OPR is developed, with owner input, to define the goals and expectations for the project.
What items should a contractor review before sending a submittal to the architect?
- Dimensions
- Materials
- Quantities
How many Type A units are required per IBC?
2% of total units