BL2 Project Reviews Flashcards

1
Q

Define Knowledge

A

Information which has been analysed and understood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Information Management

A

-Collection, storage, curation, dissemination, archiving and destruction
-Of documents, images, drawings and other sources of information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 3 types of review?

A

-Decision gate
-Benefits reviews
-Audits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Give 3 characteristics of a decision gate

A

-Held at the end of each iteration to gain agreement from the sponsor and governance board
-Check the project is still on track to deliver the benefits defined in the business case
-Linear life cycle - event driven; iterative life cycle - time bound

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Give 4 characteristics of benefits reviews

A

-Held during benefits realisation (6-12 months after handover)
-Check the project achieved benefits defined in the business case
-Actions to support benefits realisation can be determined
-Usually undertaken by the Project Sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Give 3 characteristics of audits

A

-Provide independent compliance assessment and increase stakeholder confidence
-Check the project is following the agreed governance and processes
-Conducted by personnel independent of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Give 5 factors to be reported on to ensure successful project outcomes

A

-Progress against the schedule
-Actual spending against planned spend
-Earned value
-Audit findings and number of non-conformances
-Risks and issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do the factors to be reported on typically identify?

A

What’s going well and where action is needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 6 aspects of information and data that are important?

A

-Status reporting
-Estimating the project
-Risk identification
-Problem solving and option appraisals
-Availability of information
-Knowledge and information management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is status reporting important?

A

The Project Manager can better understand the project’s status in relation to cost, schedule and quality against the acceptance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Why is estimating the project important?

A

So more realistic schedules and costs can be developed based on past data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why is risk identification important?

A

Corrective action or escalation can be determined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why is problem solving and option appraisals important?

A

Options and solutions to problems can be generated based on past experience

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why is availability of information important?

A

To inform decision-making at key points (e.g. gate reviews) and ensure the relevant information is available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why is knowledge and information management important?

A

-Understand when best to schedule quality assurance and quality control activities
-Assess what was done on past projects and when the optimum time in the life cycle is to schedule activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Give 6 reasons why activities may be re-planned after a review

A

-Achievement of planned scope isn’t to the required quality
-Motivation and satisfaction of team is low
-Performance of contractors and relationships is poor
-Committed costs and cash flow are above original forecasts
-Changes to the risk profile or cost contingency are needed because of new/changed risks
-Effectiveness of communication with stakeholders is lacking

17
Q

Decision gates:
-Held by who?
-When?
-What do they check?

A

-Project Sponsor
-End of concept and definition phases (if necessary every few months in the deployment phase)
-Check the business case is still valid and the project is on track to deliver desired outcomes

18
Q

Give 3 things that will happen in the premature closure of the project

A

-Business case will become invalid
-Funds and staff withdrawn
-Move into transition and adoption phases to make use of what’s been completed where possible

19
Q

Who carries out an internal audit and what does it include?

A

Project office or project assurance member

Review of progress, risks, problems etc.

20
Q

What happens if a project fails an audit?

A

Non-compliance will be raised and the project stopped until rectified

21
Q

Post-project review:
-When is it held?
-What does it look at?
-What does it investigate?

A

-Transition phase
-Looks at the risk register, change register and issue log to compare the original PMP to the current
-Investigates the use of processes and performance of individuals and teams

22
Q

Who undertakes the Benefits Review?

A

Project Sponsor

23
Q

Who is at the centre and disperses information flow to all stakeholders?

A

Project Manager

-Ensure the project’s outputs are being used effectively
-Verify the outcomes align with the business case