Batter Boards Flashcards

1
Q

What are the building site considerations?

A

Drainage, slope, soil, tactical emplacement and commander’s desire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the steps to place batter boards?

A
  1. a. Locate A-B corners
    b. Find point C and check the diagonal
    c. Find point D using the diagonal
  2. Place two batter boards at each corner
  3. Level all batter boards to batter board A
  4. Adjust string lines
  5. Adjust the markers
  6. Check with a plum bob
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How far off the batter boards need to be from the temporary stakes?

A

At least two feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the squaring methods?

A

3-4-5
Carpenter square
Diagonal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the least reliable squaring method?

A

Carpenter suare

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the most reliable squaring method?

A

Diagonal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly