Attribute 5 - Commercial Flashcards
What would you do if your job was going over budget / programme?
Complete a CVR (Cost Value Reconciliation)- contract review LOR specific. The difference between value and cost AKA margin. Where we stand at that point in time on specific things e.g. labour/materials/plant/staff/subcontractors/ sundries. They look at outputs.
From this- commercial decisions are made to head back towards our tender position. (This is carried out monthly).
If we are looking likely to overspend, we look at the programme and see if there are any CE’s/ EWN’s.
What we would do: run through with delivery team our issues and setup a risk reduction meeting with our client.
Explain how you compile a fee proposal for a new project.
Depends on the contract stated. With Option C start with a scope of works. Estimators would calculate the price using design info. Markups & margins added. That comes to the fee- look up estimating.
Can you talk through the elements that make up your pay rate?
Basic Salary
Travel/ mobility
Levys i.e. ICE membership/ IT account/ CITB Levy for CIS scheme
Pension
Defined cost (total cost- disallowed cost) + fee = pay rate
How do government companies get funding?
Government grants- HS2 approach the government. BBVS Option F with HS2- They hold no design responsibility for permanent works. They are to co-ordinate all the sub-contractors who deliver the works.
Can you explain the type of contract that your project was under?
Target cost Option C- Pain and gain is shared to establish collaborative working. We don’t have design responsibility unless for reinforcement and temporary works.
Both client and contractor have an immediate interest in keeping costs down to a minimum. This is why Option C was chosen.
Can you explain the difference between different types of contracts?
Design responsibilities. Traditional vs design & build.
What are the different type of NEC contracts?
Priced Contracts
A - Activity schedule
B - Bill of quantities
Target Contracts
C - Activity schedule
D - Bill of quantities
Cost Reimbursable
E - None - Based on actual cost (ECC3 defined cost)
Management Contract
F - None - Based on actual cost (ECC3 defined cost)
What is the risk allocation of NEC3 contracts?
For example, for Priced contracts (A) the risk falls on the contractor.
However for Cost Reimbursable (E) and Management contractors (F) the
risk falls on the employer.
But for Target contracts (C) the risk is shared between both parties in a ‘pain gain’ mechanism in which the percentage is decided during the tender
stage.
You are allowed CE’s on NEC option A and NEC option C so what’s different between the two options?
Option C is target cost so there is a pain & gain mechanism. CE’s lead to an increase in the target cost which in turn could lead to a share in the gain at the end of the contract.
What is an NEC option E?
Cost reimbursable. Open book, large financial risk on client.
What would the process be internally for including enough time on projects, how would you make sure you are including the correct amount?
Understanding outputs of delivery and methodology to build a current programme for the works (Clause 32). Openly telling the client this is the programme to deliver the works.
Under NEC option A and option C, can you talk me through the basic steps of a CE being agree?
EWN issued to raise concern of additional time/cost
Contractor notifies client (CE)
Followed by a meeting of discussion (Risk Reduction meeting)
Submit quotation
Quotation reviewed and agreed
Instruction is issued (CI) to deliver the works
CE implemented
Can you outline the risk allocation difference between the option A and option E on NEC contracts?
Option A- Financial burden on contractor.
Option E- Financial burden on client.
What allowances did you make for things like risk and optimism bias?
When estimating- they apply a percentage to the overall cost (make an allowance for it). They run a risk register.
How do HS2 fund their projects?
Government grants taken from the tax payer.