Attribute 1 & 2 - Engineering Knowledge Flashcards
Describe the loads acting on wall formwork during a concrete pour?
Loads on formwork can be further divided in horizontal and vertical loads. Lateral Pressure of Fresh Concrete is the main design load for formwork. The freshly placed concrete behaves temporarily like a fluid, producing a hydrostatic pressure that acts laterally on vertical forms.
Horizontal forces result from wind and concrete dumping and should be opposed by properly designed supports. There’s also lateral pressure, which is a result of accumulated depth of placed concrete.
What are the two types of piles?
End-bearing piles: These piles transmit loads directly to a strong layer of soil or rock below the surface. The bottom of the pile rests on this layer and presses against it to keep from shifting.
Friction piles: These piles transfer loads by friction between the surrounding soil and the surface of the pile.
What are push pulls props doing?
For vertical alignment and transferal of wind loads.
What is the difference between threaded bar and Dywidag?
Dywidag doesn’t work well in shear however threaded bar does. Dywidag is made from high tensile steel and has a working load of 90kN for 15mm diam. Dywidag is better used for axial loads.
What are the stages of the temporary works checks? What are you looking for?
I check if the formwork has been erected as per the drawing. Are the push pulls/ frames in the correct place, are the ties at specified height, and have the had the correct materials been used e.g. right diameter of bar. If there is any discrepancy between what is installed on site and the design, then this must be referred to the TWC or temporary works designer who will then check to see if this is acceptable prior to pouring.
What were the challenges faced when working so close to the water table?
Dewatering systems had to be put in place to constantly remove the water. This was pumped to a filtering system where the water was cleaned of silt.
How do piles transfer loads?
Transferal of load through friction between the pile surface and soil. Ground bearing piles are another type of pile that transfer loads from the structure to a hard form of ground beneath which prevents movement of the structure above.
When designing an excavation support what are the considerations designers must make?
Ground conditions, depth and how the supported excavation will deal with surcharges and ground materials.
Water ingress should also be considered as this can change the deeper you go. With the addition of hydrostatic pressure being involved.
Supports are not just necessarily trench boxes and trench sheets but also batters, these must be designed to take the weight/ surcharge of plant operating close to the edge.
What is the purpose of a redline drawing?
They record changes that have occurred over the construction phase of a project- these are manually recorded onto the design drawings and writer.
What items are included in the handover pack?
Specifications to which the building has been designed/ built, scope of works, concrete mix designs used, a copy of approvals, MAR’s, redline drawings.
Difference between permit to strike and permit to unload?
A Permit to strike refers to a formwork system that would be able to be removed once the concrete pressure no loading on the formwork/ falsework. A permit to unload involves the manual unloading of a system once it is deemed the structure can support itself e.g. RMD propping system.
How do movement joints work?
Movement or expansion joints work by allowing the structure either side to expand and contract from induced movement caused by temperature changes. They are often found between sections of buildings, roads, and bridges. This is a way to prevent cracking in a long spanning structure.
What type of piling did they use? What did they put into the void before the reinforcement cage is inserted?
CFA piles for ground bearing piles. Concrete filled the void prior to installing the cage which they then used for a crane to drop the cage into position.
What stops the deep excavation collapsing in on itself?
In this instance the auger keeps the excavation open along with the concrete once the pile has been drilled. In instances with the D-Wall, Bentonite keeps the excavation open.
How do they place the concrete in the deep excavation? What is the reason for doing it in this way?
Through the Auger. In other instances, they use a Tremie Pipe in order to eradicate the possibility of concrete segregation and a high drop height.
In being a young engineer, regarding concrete technology, what grade of concrete are you using?
C40/50 - 20mm aggregate with waterproofing additives in some cases.
What is the correlation between 7-day and 28-day concrete cube strength?
7 day strength is usually around 60-65% the 28 day strength (for a mix with GGBS).
What would you do if the gang ask the concrete delivery to add water to the mix?
I would check the ticket to see if any water was able to be added to the mix. Adding water reduces the cement/ water ratio and therefore increases the amount of water lost during the hydration process.
What are the long-term implications of adding water to the mix?
Water is required to hydrate the cement where it chemically combines to make the cement hard. Additional water is also designed into the mix in order to make it workable- this has an affect on the concrete by increasing the porosity of the mix thus reducing strength and durability of the mix. Due to the large proportion of concrete containing aggregates, it is essential to consider the moisture content of aggregates as this can have an adverse effect on the quantity of water to be added.
What is the difference between curing and hydration of concrete?
Curing is the process of maintaining adequate moisture content within a proper temperature range to aid cement hydration at early stages.
What are the benefits of using GGBS as opposed to traditional CEMI mix?
Lower carbon emissions as it is a bi-product from iron smelting
Slower hydration process which therefore reduces the temperature differential. This is useful in large volume pours as decreases the risk of early age thermal cracking.
The chemical reaction between cement and water where the cement paste hardens. Heat is a bi-product of this reaction. Cement initially starts a a paste before stiffening gradually- the hardened state of this on mass is what gives concrete its strength. Strength gain will continue provided moisture is present.
As the contractor, what actions would you take regarding the communicating to the designer?
Raising an RFI for general construction query’s, technical queries and clarifications on designs.
Can you explain the difference in principles between designing temporary works and permanent works?
Temporary works are the part of the construction project that allow the permanent works to be built. These are often removed after use.
Shorter design life
Stressed up to a higher capacity
Components are planned to be re-used
Have to be sensitive to changes and account for assembly tolerances