Appendices: CP-C-155 Coatings & Paints Flashcards
CP-C-155 Specification do not covers,,,,,,
Pipelines & Risers
Peak to Vally hight is known as,,,,,
Amplitude
Abbreviation of LAT
Lowest Astronomical Tide
Coating System for Offshore (new construction):
CS Uninsulated,,,,,
B3/B4
Coating System for Offshore (new construction):
CS Low Alloy Uninsulated,,,,,
B5
Coating System for Offshore (new construction):
CS Insulated,,,,,
B6/B7
Coating System for Offshore (new construction):
CS Fireproofed,,,,,
B8
Coating System for Offshore (new construction):
Galvanized steel,,,,,
B9/B10
Coating System for Offshore (new construction):
CS Sub sea,,,,,
B1
Coating System for Offshore (new construction):
Splash Zone,,,,,
B2
Coating System for Offshore (new construction):
Deck,,,,,
B11 to B13
Blast Cleaning:
Abrasive blast cleaning shall be in compliance with,,,
BS 7079
Blast Cleaning:
The use ,,,,,,, as a abrasive shall not be permitted
Sand
Blast Cleaning:
Abrasive shall be selected to produce a nominal surface amplitude of ,,,,,,, microns
50 to 75
Blast Cleaning:
cleaning shall to be continue to ,,,,, to the adjoining coated surface
50