Who wrote the EPP?
Traylor Aecon
Who wrote the EMP?
Hatch
When stating results, what do you want to do?
Just state results and avoid discussing what it means. Be very factual and just state results.
What is the noise by law for North Site?
Construction is exempt of the standard noise bylaw for not exceeding certain decibels (minimum 55db max 75) within permitted hours.
On the South Shaft what is the ditch classified as for the Project?
Class C watercourse- no natural watercourses were observed within South Side Shaft. The Ditch is man-made roadside drainage.
In the event of a discrepancy between any of the clauses of the environmental protection specifications and the provisions of any legislations, regulations, or municipal bylaws, which shall prevail?
Legislations, regulations and municipal bylaws
Did the south shaft surface soil sampling pre construction show any signs of contamination?
All parameters were found to be less than the BC Contaminated Sites Regulations B.C. Reg 375/96 Industrial Soil Standard
Did the North Shaft surface soil sampling pre-construction show any signs of contamination?
Numerous metals, PAHs, and TCE exceeded the BC Contaminated Sites Regulation B.C. Reg 375/96 for Parkland (PL), Commercial (CL) and/or Industrial (IL). Metals included antimony, arsenic, barium, cadmium, cobalt, copper, iron, lead, manganese, molybdenum, nickel, selenium, tin and zinc for PL, CL and IL standards/
What is the chromium (VI)