A101
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
A201
General Conditions of the Contract for Construction -Rights of the Owner -Responsibilities of the Contractor -Architect administers the contract -Changes in the work -Contract time and Substantial completions -Payments -Safety, Insurance & Bonds -Correction of the work -Terminating the contract
A Series
Owner+General Contractor
B Series
Owner+Architect Agreements
C Series
Architect + Consultant Agreement
D Series
Architect Industry Document
E Series
Digital File Management
G Series
Contract & Office Administration Forms (bidding documents, change order forms, construction change directives, etc.)
G702
Application and Certificate for Payment
- Contractor presents tp Architect to review
- Architect checks against Schedule of Values and progress observed during site visits
- Architect revises amount as needed
G704
Certificate of Substantial Completion
- Project is ready for Owner to occupy
- Start date of warranties
- Punch list of outstanding items to finish
G710
Architect’s Supplemental Instructions
-For change to contract documents without and change to contract time or sum
G701
Change order
- Make a change to contract time or sum
- Prepared by Architect
- Agreed to by Architect, Owner and Contractor
G714
Construction Change Directive
- Make a change to contract time or sum
- Prepared by Architect
- But not yet agreed to by Architect, Owner and contractor
B101
Standard Form of Agreement Between Owner and
Architect. Basic services are performed in five phases: -Schematic design
- Design development
- Construction documents
- Bidding or Negotiation
- Construction
A101 - Articles
TABLE OF ARTICLES
1 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
10 INSURANCE AND BONDS
A201 - Articles
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 OWNER
3 CONTRACTOR
4 ARCHITECT
5 SUBCONTRACTORS
6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
7 CHANGES IN THE WORK
8 TIME
9 PAYMENTS AND COMPLETION
10 PROTECTION OF PERSONS AND PROPERTY
11 INSURANCE AND BONDS
12 UNCOVERING AND CORRECTION OF WORK
13 MISCELLANEOUS PROVISIONS
14 TERMINATION OR SUSPENSION OF THE CONTRACT
15 CLAIMS AND DISPUTES