AIA Contract Documents Synopses Flashcards
A101
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
A201
General Conditions of the Contract for Construction -Rights of the Owner -Responsibilities of the Contractor -Architect administers the contract -Changes in the work -Contract time and Substantial completions -Payments -Safety, Insurance & Bonds -Correction of the work -Terminating the contract
A Series
Owner+General Contractor
B Series
Owner+Architect Agreements
C Series
Architect + Consultant Agreement
D Series
Architect Industry Document
E Series
Digital File Management
G Series
Contract & Office Administration Forms (bidding documents, change order forms, construction change directives, etc.)
G702
Application and Certificate for Payment
- Contractor presents tp Architect to review
- Architect checks against Schedule of Values and progress observed during site visits
- Architect revises amount as needed
G704
Certificate of Substantial Completion
- Project is ready for Owner to occupy
- Start date of warranties
- Punch list of outstanding items to finish
G710
Architect’s Supplemental Instructions
-For change to contract documents without and change to contract time or sum
G701
Change order
- Make a change to contract time or sum
- Prepared by Architect
- Agreed to by Architect, Owner and Contractor
G714
Construction Change Directive
- Make a change to contract time or sum
- Prepared by Architect
- But not yet agreed to by Architect, Owner and contractor
B101
Standard Form of Agreement Between Owner and
Architect. Basic services are performed in five phases: -Schematic design
- Design development
- Construction documents
- Bidding or Negotiation
- Construction
A101 - Articles
TABLE OF ARTICLES
1 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
10 INSURANCE AND BONDS