A201 Flashcards
1
Q
What’s included in the Project Manual?
A
- Title Sheet
- Table of Contents
- Bid Requirements
- Signature Sheet
- Drawing List
- List of Subcontractors (G705)
- Material Substitutions
- Contract Conditions (General, Supplementary, and Special - A201 or more)
- Contract Form
- Specification Index
* CSI Masterformat Division
* 1. Closed - Particular Brand, typically not permitted on public projects - Proprietary - by trade names, doesn’t allow for substitutions
* 2. Open - Typically provides serveral options - Performance - describes desired results, not a precise description of invididual components
* 3. Reference - Refers to quality standard that are established by testing authorities
* 4. Descriptive - Describes all components. Architect assumes total responsibility for description
* 5. Cash Allowance - Describes an amount of money required to cover the cost of some items
2
Q
What is included in the Contract Documents?
A
- Contract Conditions (A201)
- Contract Form
- Agreement - A101
- Contractor’s Qualifications - A305
- Performance and Payment Bond - A312
- Certificate of Insurance
- Bid Bond - Typically 5-10% of the Contract Sum to be collected if the winning bidder refuses to sign the Contract
- Specification Index
- Working Drawings (the Architect’s prepared CD set)
- Addenda
- Contract Modifications
- Change Order
- Construction Change Directives
Minor changes are those after the Contract is signed, yet too minor to affect Contract Sum or Time.
3
Q
What is included in a Construction Documents
A
- Project Manual
- Working Drawings
- Addenda
- Contract Modification
4
Q
What is included in the Bidding Documents?
A
- Project Manual
- Bid Requrements
- Invitation to Bid
- Information Available to Bidders
- Instructions to Bidders
- Bid Forms
- Bid Supplements
- Bid Requrements
- Working Drawings
- Addenda
Contract Modifications (Change Order, Change Directives) is not included because at this point, the Contract has not been signed yet - It’s in the Bidding Phase!
5
Q
Critical Days/Decisions in the Life of a Project
Assuming the most straightforward DBB project.
This is a comprehensive list of a project life
A
- Decide the delivery method
- The Owner provides project expectations, documentations for existing site conditions
-
Agreement with the Architect (B101 if traditional DBB)
* Design Phase- Programming
- SD
- DD
- CD
- Pre-Bid
- Questions and clarifications must be within (7)days before the Bid Date
- Addendum
* Bidding Phase - Owner provides evidence of ability to pay
- Contractor requests lien information
- In (15) days Owner provides lien information
- Owner pays for assessment, approvals, tests, surveys, etc. to determine project feasibility (Geo-Technical, Land survey)
- Contractor’s substitution request (if any) - must be submitted to the Architect at least (10) days before the Bid Date
- If the Owner approves the alternate materials, Architect must issue an Addendum to all bidders (4) days prior to Bid Date. Refer to A701, Article 3.4.3
- Contractor clarification request - must be submitted to the Architect at least (7) days before the Bid Date
- Bid Date (deadline for bid)
- Contractor’s qualification statement (A305)
- Bid Awarded - typically to the lowest bid (if using A101)
- Execution of the Contract (prime contract signed)
- Contractor submits subcontractor list
- Owner pays for repreoduction of drawings to be returned to the Architect as their copyrighted material
- Pre-Construction conference - owner submits financial evidence of sufficient funding
- Contractor provides Certificate of Insurance - the Owner will be given at least (30) days notice before insurance policies are cancelled
* Construction Phase - Commencement of Construction
- If hazardous material discovered, the Contractor must immediately stop the Work in the affected area and report to the O&A no later than (14) days after first discovery - A201, 3.7.4.
- Contractor submits Schedule of Values
- Contractor submits Application for Payment (G702) - no less than (10) days prior to the Date of Payment established by the Schedule of Values
- Architect issues Certificate for Payment (G702) - no less than (7) days
- Progress payment
- Subcontractor’s RFI
- Permits and Fees paid by Contractor
- Repeated Application and Certification for Payment for progress (G702)
- Submittals
- If any, Change in Scope of the Project - Change order (G701) or Construction Change Directive (G714)
- If any (typically yes), minor change - Architect’s Supplemental Instructions (ASI, G710)
- Certificate of Substantial Completion (G704)
- Final Application for Payment
- Final Inspection
- Final Certification for Payment
- Warranties and Guarantees
- Contractor’s Testaments to Completion
- Final Payment = Project Acceptance - Project Close-Out
- 1 year Post-Completion