9.Access Work Plan Flashcards

1
Q
  1. Access Work Plan
A

9.1. An access work plan shall be completed prior to beginning all rope access work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Access Work Plan
A

9.2. The access work plan shall be maintained at the worksite and available to all affected persons.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Access Work Plan
A

9.3. The access work plan shall be updated as necessary during the course of rose access work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Access Work Plan
A

9.4. A documented review of the access work plan by rope access technicians shall be conducted prior to each work shift and after any updates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Access Work Plan
A

9.5. The access work plan should be reviewed by any person affected by the rope access work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Access Work Plan
A

9.6. For new work, a site survey should be conducted to help determine:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Access Work Plan
A

9.6.1. The nature of the work environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Access Work Plan
A

9.6.2. Feasibility of the means of access.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Access Work Plan
A

9.6.3. Foreseeable hazards to rope access technicians and others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Access Work Plan
A

9.7. The access work plan shall, at a minimum, consist of the following:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Access Work Plan
A

9.7.1. Work method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Access Work Plan
A

9.7.2. Risk assessment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Access Work Plan
A

9.7.3. Special permits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. Access Work Plan
A

9.7.4. Rescue plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Access Work Plan
A

9.8. Work Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. Access Work Plan
A

9.8.1. The work method, shall, at a minimum, provide:

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Access Work Plan
A

9.8.1.1. Members of the work team by name and identify their roles and level of training.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. Access Work Plan
A

9.8.1.2. The hazard and fall zones is accordance with Section 10.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. Access Work Plan
A

9.8.1.3. The communication plan in accordance with Section 11.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. Access Work Plan
A

9.8.1.4. Required rope access systems in accordance with Section 12.

21
Q
  1. Access Work Plan
A

9.8.1.5. Required rope access equipment in accordance with Section 13.

22
Q
  1. Access Work Plan
A

9.8.1.6. Required tools and other materials in accordance with Section 14.

23
Q

9.Access Work Plan

A

9.8.1.7. Required personal protective equipment(PPE).

24
Q
  1. Access Work Plan
A

9.9. Risk Assessment

25
Q
  1. Access Work Plan
A

9.9.1. The work method and work environment shall be reviewed to identify all hazards that rope access technicians or others may be exposed to during the course of work.

26
Q
  1. Access Work Plan
A

9.9.2. Modifications to the work method and / or controls shall be identified to either eliminate the identified hazards, or to mitigate the associated risk to an acceptable level.

27
Q
  1. Access work Plan
A

9.9.3. If new hazards arise during the course of work, work shall be stopped until appropriate controls have been identified, documented , and implemented .

28
Q
  1. Access work Plan
A

9.9.4. The review of the work method, shall consider, at a minimum:

29
Q
  1. Access work Plan
A

9.9.4.1. The time required for the work at any one location.

30
Q
  1. Access work Plan
A

9.9.4.2. Whether adjacent work may affect the planned work.

31
Q
  1. Access work Plan
A

9.9.4.3. Whether providing security to the anchorage location is warrented.

32
Q
  1. Access work Plan
A

9.9.4.4. Whether any public safety provisions are required.

33
Q
  1. Access work Plan
A

9.9.4.5. Hazards associated with the use of tools, work equipment, and materials required for the work.

34
Q
  1. Access work Plan
A

9.9.5. The review of the work environment shall consider, at a minimum:

35
Q
  1. Access work Plan
A

9.9.5.1. Adverse weather.

36
Q
  1. Access work Plan
A

9.9.5.2. the effects of wind on rope access systems, positioning, and work equipment, and materials required for the work.

37
Q

9.Access work Plan

A

9.9.5.3. Lock out tag out(LOTO) requirements.

38
Q

9.Access work Plan

A

9.9.5.4. Potential loose material.

39
Q
  1. Access work Plan
A

9.10. Special permits

40
Q
  1. Access work Plan
A

9.10.1. Special permits shall be determined by the work being conducted.

41
Q
  1. Access work Plan
A

9.10.2. Special permits include:

42
Q
  1. Access work Plan
A

9.10.2.1. Confined space.

43
Q

9 . Access work Plan

A

9.10.2.2. Hot work.

44
Q
  1. Access work Plan
A

9.10.2.3. Live electrical work.

45
Q
  1. Access work Plan
A

9.11. Rescue Plan

46
Q
  1. Access work Plan
A

9.11.1. The work method and risk assessment shall be reviewed to identify where rescue could be required.

47
Q
  1. Access work Plan
A

9.11.2. Modifications to the work method and/or controls should be identified to facilitate prompt rescue.

48
Q
  1. Access work Plan
A

9.11.3. The rescue plan shall provide procedure’s for prompt rescue from the foreseeable scenarios in accordance with Section 16.