9.0 Cost Estimation and Predictability Flashcards

1
Q

What is a Project Cost Estimate?

A
  • A prediction of the most likely total cost of the identified scope of work for a project
  • The philosophy of project cost estimating is to produce the best cost estimates to the level of project development, inclusive of contingencies reflective of the project risks and the project phase, using the most accurate and complete project and pricing information available at the time the estimate is prepared
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Purpose of a Project Cost estimate

A

To provide a basis for developing, amending, or reviewing a project budget. A cost estimate is a key component of the project business cases, as it is the foremost document to justify/support funding allocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Contractor, Developer, City’s cost estimate

A
  • Contractor - estimate too high & the bid may go to someone else; estimate too low, wins the big & later he wishes it went to someone else
  • Developer - estimate too low, additional financing cost down the road or lose of profit
  • City - too high estimate could lead to killing a project, political ramification, lose of public trust
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Accuracy and completeness of cost estimating

A
  • The importance of accuracy and completeness cannot be overstated
  • An estimate based on incomplete or incorrect information can make an already programmed and committed to project difficult or impossible to deliver, if early estimates prove to be significantly low
  • Conversely, when early estimates prove to be significantly high, it can lead to killing an important project
  • An accurate and complete cost estimate goes a long way toward supporting the successful delivery of a project within its approved budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project life cycle phases

(see photo)

A
  1. Pre Project work (corridor)
  2. Planning and evaluation
  3. Design and engineering
  4. Property acquisition and construction
    * As knowledge increases, risk typically decreases
    * Accuracy improves as knowledge increases
    * Cost estimates need to be continually revised to keep them current
    * Each revision should result with a greater level of confidence than the preceding estimate
    * Each successive estimate should fall within the range of accuracy of the previous estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Quality:

Cost estimators should…

Principles of Project Cost Estimating

A
  • Apply expert judgement to the estimate and the assumptions made in developing it
  • Incorporate appropriate quality control processes into the estimating process
  • Appropriately consider and quantify the risks and uncertainties of the project
  • Present the estimate in an easily understood format
    Be able to defend the estimate and the basis for the decision and assumptions therein, if asked
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Integrity

Principles of Project Cost Estimating

A
  • Project cost estimates should be prepared using a high standard or professional and ethical integrity
  • They should not be prepared by anyone who may be, or may be perceived to be in conflict of interest
  • Project cost estimates should be presented in a manner that is easily understood
  • Where possible project cost estimates should be prepared using a team approach, employing expertise from appropriate disciplines for the major project components
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contingency

Principles of Project Cost Estimating

A
  • Contingency is generally understood to be an amount of money added to an estimate to cover items of cost which are not known exactly at the time the estimate is developed, but which will likely occur during the life of the project
  • It is intended only for the scope as defined in the estimate, it is not intended to cover scope changes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

An estimate assumes things as….

Principles of Project Cost Estimating

A
  • Errors will not be made and quantities will not change
  • Resources will be available
  • The work will be done according to the execution plan
  • The project is well defined and decisions will be made on time
  • Contractors work will flow smoothly and produce deliverable per the schedule
  • Contractor will have materials, equipment, and information as per the schedule
  • Contingency is meant to cover likely variations to these assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does contingency include?

A
  • Normal design development changes
    • Normal variations in project execution
    • Normal variations in estimating (e.g. between estimated and actual quantities and costs)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does contingency EXCLUDE?

A
  • Significant changes in scope
    • Major changes in project execution
    • Extraordinary variations in cost (escalation)
    • Major (unexpected) work stoppages
    • Disasters (earthquakes, tornadoes, etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Contingency point to remember

A
  • Project cost estimates should always include contingency to cover certain uncertainties and risks
    • Contingency is an item in a cost estimate like any other. It is bet presented as a separate line to clearly identify it
    • Contingency evolves with the level of project understanding
    • An estimate that contains too much contingency is overpriced; such estimates can negatively impact project “go/no-go” decisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

AACE Process Industry Estimate Classification

A

See photo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Estimate Variance Matrix

A

Class of estimates

D, C, B, A

Based on concept sketch design, 33% design development, 66% design development, 100% complete tender documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Factors influencing an estimate

A

See photo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Cost predictability in construction

A

*“the prediction of a construction cost estimate, as compared to the median of competitive bids”
* Where Prediction is defined as “an assertion on the basis of data, theory or experience, but in advance of proof”

17
Q

Issues and Considerations in cost predictability

A

Local or national construction industries are becoming increasingly affected by global trends and influences, which can create significant and unexpected volatility and unpredictability in the construction marketplace

18
Q

Examples of such market volatility would include:

A
  • The abnormal cost escalation in BC during 2006 leading up to the Vancouver Olympics
    • The unprecedented run-up in almost all construction material prices in 2008, especially for steel and oil-based products, across the world
    • The equally unprecedented and sudden global financial crisis, and resulting potential temporary collapse of both the commodity and construction markets in 2008-2009
    • NAFTA renegotiation/Trans-Pacific Trade Agreement
19
Q

To manage Scope creep and absorb its impact

A
  • Immediately adjust for any changes
    • Use value engineering techniques with input from various sectors
20
Q

The following two escalation contingencies should be taken into consideration

A
  1. Market escalation up to the bid
    1. Embedded escalation within bid prices
21
Q

Issues and considerations in cost predictability

A
  1. Consideration of local or regional market influences
    1. Current and accurate information should be shared between stakeholders
    2. Cost estimates should be prepared during tender period for changes to schedule or addenda
    3. Incomplete/uncoordinated bid documents, causing different interpretations
    4. Failure to recognize the appropriate class of estimate
    5. Fast-tracking projects or proceeding with a project before it is well defined
    6. Project objectives or program not clearly defined when developing the intial budget
    7. Scope creep - growth in project objectives or programs during design development
    8. Proper use of contingencies
    9. Mistake of designing to maximum of the budget
    10. No consideration or misuse of data about similar projects
    11. Actual errors in the estimate or bid preparation
    12. Ensure that the estimate is produced by a qualitifed individual
    13. Outdated estimate used
    14. No consideration for normal cost inflation
    15. Pressure to meet limited budget
22
Q
  1. No consideration or misuse of data about similar projects
A

When using budgets from previous projects one should take into account lessons learned. This applies in particular to the Class D estimate stage

23
Q
  1. Actual errors in the estimate or bid preparation
A

Double check and overview all estimates before submission to avoid making errors

24
Q
  1. Outdated estimate used
A

Projects and estimates that are delayed or shelved need to be updated to make the proper allowances for current market conditions

25
Q
  1. No consideration for normal cost inflation
A

Consideration for industry specific cost inflation should be given

26
Q
  1. Pressure to meet limited budget
A

Estimates should not be altered to meet limited budgets. If the estimate exceeds the budget, owner should achieve the intended result by either increasing the budget or modifying the scope of work

27
Q

Recommendations for improved cost predictability

A
  1. Utilize qualified estimating personnel throughout the life of the project
    1. Ensure all stakeholders have input early and often. Clear definition of project objectives, program and scope will avoid potentially expensive surprises, such as scope growth
    2. Give designers sufficient time to finalize bid documents
    3. Consider developing and maintaining a usable construction cost database
    4. Include sufficient contingency to address market volatility, timing of construction, and other exclusions in the estimate
28
Q

Before tender

A
  • Consider possible scope variations in the tender as a contingency to adjust to the owner’s budget
    • Give designers sufficient time to finalize 100% big documents for the pre-tender estimate
    • Allow cost consultants or estimators sufficient time to prepare and finalize pre-tender estimates
29
Q

During Tender

A
  • Keep the cost consultant involved during the tender period
    • Monitor addenda changes and bidding environment
    • Revise estimates to reflect scope changes and addenda
30
Q

After tender

A
  • Involve the cost consultant in the post tender review
    • Analyze bid results against estimates for lessons learned
    • Keep a record of historical estimate versus bid data
31
Q

When a capital project gets completed consider carrying out a …

A

post-completion assessment to determine whether the project was carried out successfully, how contractors performed, the risks encountered and whether you have achieved overall project objectives

32
Q

Cost predictability guarantee

A

There is no guarantee that pre-tender estimates will precisely match bid prices, just as there is no expectation that all bid prices will be the same. In reality, there are too many variables influencing final bid prices to expect 100% accuracy. However, there are many proven recommendations and methodologies one can follow to help improve and define the cost predictability of projects