9.0 Cost Estimation and Predictability Flashcards
What is a Project Cost Estimate?
- A prediction of the most likely total cost of the identified scope of work for a project
- The philosophy of project cost estimating is to produce the best cost estimates to the level of project development, inclusive of contingencies reflective of the project risks and the project phase, using the most accurate and complete project and pricing information available at the time the estimate is prepared
Purpose of a Project Cost estimate
To provide a basis for developing, amending, or reviewing a project budget. A cost estimate is a key component of the project business cases, as it is the foremost document to justify/support funding allocation
Contractor, Developer, City’s cost estimate
- Contractor - estimate too high & the bid may go to someone else; estimate too low, wins the big & later he wishes it went to someone else
- Developer - estimate too low, additional financing cost down the road or lose of profit
- City - too high estimate could lead to killing a project, political ramification, lose of public trust
Accuracy and completeness of cost estimating
- The importance of accuracy and completeness cannot be overstated
- An estimate based on incomplete or incorrect information can make an already programmed and committed to project difficult or impossible to deliver, if early estimates prove to be significantly low
- Conversely, when early estimates prove to be significantly high, it can lead to killing an important project
- An accurate and complete cost estimate goes a long way toward supporting the successful delivery of a project within its approved budget
Project life cycle phases
(see photo)
- Pre Project work (corridor)
- Planning and evaluation
- Design and engineering
- Property acquisition and construction
* As knowledge increases, risk typically decreases
* Accuracy improves as knowledge increases
* Cost estimates need to be continually revised to keep them current
* Each revision should result with a greater level of confidence than the preceding estimate
* Each successive estimate should fall within the range of accuracy of the previous estimate
Quality:
Cost estimators should…
Principles of Project Cost Estimating
- Apply expert judgement to the estimate and the assumptions made in developing it
- Incorporate appropriate quality control processes into the estimating process
- Appropriately consider and quantify the risks and uncertainties of the project
- Present the estimate in an easily understood format
Be able to defend the estimate and the basis for the decision and assumptions therein, if asked
Integrity
Principles of Project Cost Estimating
- Project cost estimates should be prepared using a high standard or professional and ethical integrity
- They should not be prepared by anyone who may be, or may be perceived to be in conflict of interest
- Project cost estimates should be presented in a manner that is easily understood
- Where possible project cost estimates should be prepared using a team approach, employing expertise from appropriate disciplines for the major project components
Contingency
Principles of Project Cost Estimating
- Contingency is generally understood to be an amount of money added to an estimate to cover items of cost which are not known exactly at the time the estimate is developed, but which will likely occur during the life of the project
- It is intended only for the scope as defined in the estimate, it is not intended to cover scope changes
An estimate assumes things as….
Principles of Project Cost Estimating
- Errors will not be made and quantities will not change
- Resources will be available
- The work will be done according to the execution plan
- The project is well defined and decisions will be made on time
- Contractors work will flow smoothly and produce deliverable per the schedule
- Contractor will have materials, equipment, and information as per the schedule
- Contingency is meant to cover likely variations to these assumptions
What does contingency include?
- Normal design development changes
- Normal variations in project execution
- Normal variations in estimating (e.g. between estimated and actual quantities and costs)
What does contingency EXCLUDE?
- Significant changes in scope
- Major changes in project execution
- Extraordinary variations in cost (escalation)
- Major (unexpected) work stoppages
- Disasters (earthquakes, tornadoes, etc.)
Contingency point to remember
- Project cost estimates should always include contingency to cover certain uncertainties and risks
- Contingency is an item in a cost estimate like any other. It is bet presented as a separate line to clearly identify it
- Contingency evolves with the level of project understanding
- An estimate that contains too much contingency is overpriced; such estimates can negatively impact project “go/no-go” decisions
AACE Process Industry Estimate Classification
See photo
Cost Estimate Variance Matrix
Class of estimates
D, C, B, A
Based on concept sketch design, 33% design development, 66% design development, 100% complete tender documents
Factors influencing an estimate
See photo