8.2 Black Start Definitions & Procurement Flashcards

1
Q

How does PJM define a black start resource?

A
  • can start w/o outside electrical supply

- demonstrated ability to automatically remain operating, at reduced levels, when disconnected from the grid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How soon does a GOP with blackstart resource have to notify TO of changes to capability? (NERC)

A

w/in 24 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often must blackstart resources be tested per NERC?

A

At least once every 3 calendar years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the training requirements for personnel responsible for startup of blackstart units? (NERC)

A

Minimum 2 hours of training every 2 calendar years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PJM requires a critical black start unit must be able to close its output breaker to a dead bus within ____ hours of request from TO or PJM

A

3 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How often does PJM require testing of blackstart units (different than NERC requirement)

A

Annually

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How long does PJM require the black start unit has the ability to run?

A

16 hours

or as defined by TO restoration plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What comprises the minimum critical black start requirement for each transmission zone?

A
  • Critical cranking power load
  • Off site nuclear station light & power (to maintain safe shutdown)
  • Critical natural gas infrastructure (i.e. electric compressors)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is critical load comprised of?

A
  • Cranking power for generating units with hot start time of 4 hours or less
  • Off-site nuclear station light & power
  • Gas infrastructure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is priority load comprised of?

A
  • Cranking power to generation > 4 hour start up time
  • Power to electric infrastructure ( substations etc)
  • Critical comms equipment
  • Critical command and control facilities
  • Underfrequency load shed circuits
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the amount of black start resource required in a given transmission zone?

A

110% of critical load requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the minimum number of black start units that PJM will allocate to each transmission zone with a critical load requirement?

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is cross zonal coordination used for?

A

When a blackstart resource from a different TO zone is used for a TO’s critical load requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe Level 1 CZC

A

Using outside blackstart resources to meet critical load requirements. Both supplier and receiver document cranking path to respective border.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe Level 2 CZC

A

Supplying black start generation to critical and/or customer load pockets across TO zones.

Both TO’s will document coordination in their restoration plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe Level 3 CZC

A

Fully aggregate TO restoration plans into a combined plan for a newly defined restoration region.

Merging two or more existing TO zones to have only one restoration plan for the combined area.