7.5 Supplementary Status Report (SSR) Flashcards
1
Q
What is the purpose of the SSR?
A
To provide a snapshot of current generating capacity and resource limitations.
PJM uses to prepare capacity/load/reserve projection when potential emergencies exist.
2
Q
How are SSR’s requested?
A
Via All-Call
3
Q
How is SSR reporting handled?
A
eDART is preferred. A fax or call could be alternate methods
4
Q
What are the 5 Parts of data to be reported in the SSR?
A
A: Instantaneous Capacity Check B: Energy Loaded E: Capacity Changes to Part A Capacities F: Expected additional capacity G: Resource limited units