7 Themes Flashcards

1
Q

What are the seven themes in PRINCE2?

A
  • Business case
  • Organization
  • Quality
  • Plans
  • Risk
  • Change
  • Progress

Themes are areas of project management that must be addressed continuously throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are PRINCE2 themes based upon?

A

The 7 principles

Themes are applied by using the 7 processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of the Business Case theme in PRINCE2?

A

To justify the project’s existence and ensure it remains viable throughout its lifecycle

It addresses the justification for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which PRINCE2 theme focuses on the project’s structure and roles?

A

Organization

It defines the team’s roles and responsibilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does the Quality theme in PRINCE2 ensure?

A

That the project deliverables meet the required standards and stakeholder expectations

Quality is assessed throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which theme is concerned with what needs to be achieved and how it will be delivered?

A

Plans

Plans outline the project’s objectives and the steps to achieve them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the focus of the Risk theme in PRINCE2?

A

Identifying, assessing, and managing risks that could impact the project

Risk management is crucial for project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does the Change theme in PRINCE2 address?

A

Managing changes to the project’s baseline

It ensures that changes are controlled and documented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of the Progress theme in PRINCE2?

A

To monitor and control the project’s progress against the plan

It enables informed decision-making regarding project status.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Fill in the blank: PRINCE2 themes are applied by using the _______.

A

[key learning term: 7 processes]

The processes guide the application of themes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of a business case in a project?

A

Creates and maintains a business justification for the project

A business case ensures that project outcomes are achieved and benefits realized.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the project organization structure define?

A

Defines the project organization structure and roles

This includes the roles of the Project Board, Executive, Senior User, Senior Supplier, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the role of stakeholder communication in project management?

A

Defines the approach to communicating and engaging with stakeholders

Effective communication is essential for stakeholder engagement and project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does the project quality management approach specify?

A

Defines the project quality management approach

This includes specifying prioritized acceptance criteria for the final project product(s).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the significance of plans in project management?

A

Plans enable the business case to be realized

Different levels of plans facilitate communication and control from the differing perspectives of the project organization.

17
Q

What does the risk management approach define?

A

Defines the risk management approach and ensures that project risks are identified, assessed and controlled

This is crucial for proactive risk mitigation in projects.

18
Q

Fill in the blank: The change control approach ensures that issues are _______.

A

[captured, assessed and controlled]

19
Q

How is project progress measured?

A

Defines the way that the project progress is measured and compared to performance targets

Progress measurement enables a forecast of the continuing project viability.