7 Processes Flashcards

1
Q

What are the seven processes described in PRINCE2?

A
  1. Starting Up A Project
  2. Initiating A Project
  3. Directing A Project
  4. Managing A Stage Boundary
  5. Controlling A Stage
  6. Managing Product Delivery
  7. Closing A Project

These processes outline the steps taken in project management according to PRINCE2 methodology.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does the ‘Starting Up A Project’ process involve?

A

Establishing the project mandate and ensuring alignment with corporate or program management

This process is crucial for defining the project’s initial scope and objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the main focus of the ‘Initiating A Project’ process?

A

Providing the project initiation documentation and planning the project

This step lays the groundwork for project execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which process is responsible for overseeing the project from a strategic level?

A

Directing A Project

This process ensures that the project remains aligned with business objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does ‘Managing A Stage Boundary’ entail?

A

Reviewing project progress and planning for the next stage

This process helps in assessing the project’s current status and preparing for upcoming tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the focus of the ‘Controlling A Stage’ process?

A

Monitoring and controlling the progress of the current stage

This ensures that the project stays on track and within budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does ‘Managing Product Delivery’ involve?

A

Ensuring that the project’s products are delivered as per the agreed specifications

This process is critical for maintaining quality and meeting stakeholder expectations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the final process in the PRINCE2 methodology?

A

Closing A Project

This process includes finalizing all activities and documenting lessons learned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

True or False: The ‘Controlling A Stage’ process is essential for managing product delivery.

A

False

While both processes are important, ‘Controlling A Stage’ focuses on monitoring progress rather than product delivery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Fill in the blank: The _______ process is concerned with reviewing project authors and benefits.

A

Managing A Stage Boundary

This process involves assessing the current stage and planning for the next one.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which role in the project management team is responsible for making decisions?

A

The project board

The project board is responsible for strategic decisions throughout the project’s lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly