6 - Project Schedule Management Flashcards
Activity list
The primary output of breaking down the WBS work packages.
Alternative analysis
The identification of more than on solution. Consider roles, materials, tools and approaches to the project work.
Analogous estimating
A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be. Analogous estimating is more reliable however than team member recollections. Analogous estimating is also know as top-down estimating and is a form of expert judgment.
Bottom-up estimating
The most accurate time-and-cost estimating approach a PM can use. This estimating approach starts at “the bottom” of the project and considers every activity, its predecessor and successor activities, and the exact amount of resources needed to complete each activity.
Control account
A WBS entry that considers the time, cost and scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance to measure the overall performance for the deliverables within that control account. The specifics of a control account are documented in a control account plan.
External dependencies
These are dependencies that are outside of the project’s control. Ex: delivery of equipment from vendor, the deliverable of another project, or the decision of a committee
Fast tracking
A schedule compression method that changes the relationship of activities. With fast tracking, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap.
It can be done y changing the relation of activities from FS to SS or even FF or by adding lead time to downstream activities. However, fast tracking does add risk to the project.
Finish-to-finish
An activity relationship type that requires the current activity to be finished before its successor can finish.
Finish-to-start
An activity relationship type that requires the current activity to be finished before its successor can start.
Fragnet
A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Also called a subnet.
Free float
This is the total time single activity can be delayed without affecting the early start of its immediately following successor activities.
Hard logic
Logic that describes activities that must happen in a particular order. Ex: dirt must be dug before the foundation can be built. Also know as mandatory dependency.
Internal dependencies
Internal relationships to the project or the organization. Ex: the team must create the software as part of the project’s deliverable before the software can be tested for quality control.
Lag time
Positive time that moves 2 or more activities further apart.
Late finish
The latest a project activity can finish.
Used in the backward pass procedure to discover the critical path and the project float.
Late start
The latest a project activity can start.
Used in the backward pass procedure to discover the critical path and the project float.