12 - Project Procurement Management Terms Flashcards

1
Q

Alternative dispute resolution

A

Trying to reach a settlement through mediation or arbitration, for an issue or claim.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bid

A

Issued from seller to buyer. Provides a price for the work in question. Determining factor in the decision making process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bidder conference

A

A meeting of all project’s potential vendors to clarify the contract statement of work, and details of the contracted work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Claims

A

Disagreements between vendor and buyer, usually about a change (who did it? did it really happen?).
Also called disputes/appeals, monitored and controlled throughout the project in accordance with the contract terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contract

A

Formal agreement between the vendor and buyer. Can be oral or written (written is preferred).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract change control system

A

Defines the procedures for how the contract may be changed.
The process includes forms, documented communications, conditions within the project, business or marketplace that justify the need for change, dispute resolution procedures, and the procedures for getting the changes approved within the performing organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract statement of work (SOW or CSOW)

A

This document requires the seller to fully describe the work to be completed and/or the product to be supplied. The SOW becomes part of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost plus award fee contract

A

A contract that pays the vendor all costs for the project, but also includes a buyer-determined award fee for the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost plus fixed fee contract

A

A contract that requires the buyer to pay for the cost of the goods & services procured plus a fixed fee for the contracted work.
The buyer assumes the risk of cost overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost plus incentive fee

A

A contract that requires the buyer to pay a cost for the procured work, plus an incentive fee (bonus) if the terms & conditions are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost plus percentage of costs

A

A contract that requires the buyer to pay for the costs of the goods & services procured plus a percentage of the costs.
The buyer assumes all of the risks for cost overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Direct costs

A

Costs incurred that are necessary for the project to exist. (e.g. equipment, salaries etc…)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fixed price contracts

A

AKA firm fixed-price and lump-sum contracts.

These are agreements that define a total price for the product the seller is to provide.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fixed price incentive fee

A

A fixed price contract with opportunities for bonuses, for meeting goals on costs/schedule/and other criteria.
These contracts usually have a price ceiling for costs and associated bonuses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Fixed price with economic price adjustments

A

A fixed price contract with a special allowance for price increases based on economic reasons such as inflation or the cost of raw materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Force majeure

A

An “act of God” that may have a negative impact on a project.

17
Q

Independent estimates

A

Referred as “should cost” estimates. Created by the performing organization or external experts to predict what the cost of the procured product should be.

18
Q

Indirect costs

A

These are costs attributed to the cost of doing business.

19
Q

Invitation for Bid (IFB)

A

From buyer to vendor. Requests the seller to provide a price for the procured product/service.

20
Q

Letter contract

A

Allows the vendor to begin working on the project immediately. Often used as a stopgap solution.

21
Q

Letter of intent

A

A letter of intent is not a contract, but a letter stating that the buyer is intending to create a contractual relationship with the seller.

22
Q

Make-or-Buy decision

A

A process in which the project management team determines the cost-effectiveness, benefits, and feasibility of making a product or buying it from a vendor.

23
Q

Privity

A

Contractual relationship between the buyer and the seller is considered to be confidential and secret.

24
Q

Procurement management plan

A

A project management subsidiary plan that documents the decision made in the procurement planning processes.

25
Q

Procurement planning

A

A process to identify which parts of the project warrant procurement from a vendor

26
Q

Proposal

A

A document that the seller provides to the buyer. It includes more than just a fee for the proposed work. It also includes information on vendor’s skills, reputation, ideas on how the vendor can complete the contracted work.

27
Q

Purchase order (PO)

A

A form of unilateral contract that the buyer provides to the vendor, showing that the purchase has been approved by the buyer’s organization.

28
Q

Quotation

A

From seller to buyer. Price is the determining factor in the decision-making process

29
Q

Request for Proposal (RFP)

A

From buyer to vendor. Requests the vendor to provide a proposal to complete the procured work, or to provide the procured product.

30
Q

Request for Quote (RFQ)

A

From buyer to vendor. Requests the vendor to provide a price fr the procured product/service.

31
Q

Request for Info (RFI)

A

Asking for additional information about the vendor’s products and/or services.

32
Q

Risk-related contractual agreements

A

When using transference, a risk related contractual agreement is created between the buyer and vendor.

33
Q

Screening system

A

A tool that filters or screens out vendors that do not qualify for the contract.

34
Q

Seller rating system

A

Used by organizations to rate prior experience with each vendor that they have worked with in the past. The seller rating system can track performance, quality ratings, delivery, and even contract compliance.

35
Q

Terms of reference

A

Defines the obligations for the vendor, what it will provide, and all of the particulars of the contracted work.
It is similar to statement of work

36
Q

Time and materials contract

A

A contract type in which the buyer pays for the time and materials for the procured work.
Used for simple contracts, needs to have a not-to-exceed clause, or the buyer assumes the risk for cost overruns.

37
Q

Weighting system

A

Weights are assigned to the values of the proposals, and each proposal is scored. Prevents the personal preference of the decision maker.